Review of safety at Sheppey Crossing to take place

29/01/2015
Highways Reporters

Roads Minister John Hayes has agreed to undertake an urgent review into how the design and construction of the Sheppey Crossing was conducted.

This follows a claim that the Highways Agency failed to adopt recommendations made in its own Road Safety Audit and ignored the safety advice of Kent Police when design and construction of the Sheppey Crossing took place.

This claim was made in an email sent by a retired police officer, Richard Denyer, who contacted Sittingbourne and Sheppey MP Gordon Henderson following a radio interview the MP made in which he called for a review of safety on the bridge following a huge pile up in 2013 and a tragic accident last year in which a mother and son were killed.

Mr Denyer, who was the Kent Police Traffic Management Officer for the Swale Area during the period when the Sheppey Crossing was being built, alleged he had weekly meetings with the Highways Agency during which he raised his concerns regarding the safety of the bridge.

For instance, he raised concerns about the lack of a refuge should a motor vehicle breakdown on the bridge.

He said: “There was not any places of safety for stranded motorists. No place for stranded motorists and nowhere to walk off the bridge and summon assistance.”

Mr Denver expressed concerns also about visibility on the bridge, maintaining that a motorist travelling over the brow of the bridge from Sheppey towards Iwade who was confronted by a stationary vehicle would have a maximum of 150 metres in which to react by taking avoiding action or stopping. This, he explained, did not take into account the likelihood of other vehicles already being stationary behind the broken down vehicle.

Mr Denyer alleged in his email that right up until the official opening of the bridge he requested the following safety features:-

1) Low level fluorescent strip lighting along the inside of the concrete parapet

2) A safe walkway for stranded motorists to get off the bridge

3) Emergency telephones at regular intervals on the bridge

4) Matrix signs on the approach to the bridge from either side to warn of fog and other dangers

5) Gates at either end of the bridge, similar to the gates that protect motorway slip roads, which could be closed in an emergency.

Mr Denyer alleged also that in the month leading up to the bridge’s opening Highways Agency staff admitted, but added that construction was seriously over budget and there was no money left to make any of the changes he had requested.

His allegations were backed up by information sent to Mr Henderson by Minster Parish Council, which had been obtained under the Freedom Of Information Act.

It revealed the Road Safety Audit (RSA) Stage 2 report made to the Highways Agency by Mott MacDonald in 2005 expressed concern about the gradient of the bridge, which could result “in a higher than expected rate of nose to tail type collisions.”

Mott MacDonald also recommended that there should be more signage to warn of problems in high winds, fog and mist. But these recommendations were rejected.

Mr Henderson said: “These documents make clear that the Highways Agency was warned about the safety risks presented by the design of the bridge and it is clear also that doing something to introduce the recommended safety measures was rejected on the grounds of cost.

“Frankly, I think it is a scandal also that a government department should ignore the advice of the police and its own Road Safety Audit on such an important issue in order to save money.

“I think whoever took the decision to put money before safety has a number of serious questions to answer and I want to see the reasons for that decision investigated.

“Last week I met with the Roads Minister, the Rt Hon John Hayes MP, and he has agreed to undertake an urgent review into how the design and construction of the Sheppey Crossing was conducted. Mr Hayes promised also to undertake an immediate review of what steps are needed to make the bridge safe.

“I am delighted with the Minister’s promise because right now I am less interested in recriminations against those who so badly messed up the design and construction of the bridge than I am in seeing put in place as soon as possible some of the safety measures that we have been calling for since the multi car pile-up in 2013.”

In a statement, the Highways Agency said: "Safety is always our top priority, and we remain absolutely committed to keeping journeys on the Sheppey Crossing safe and reliable. The bridge was designed and built in compliance with all relevant design and safety standards, and we keep its safety record continually under review.

"The fog-related incident on the Crossing in September 2013 was fully investigated by the police; the investigation concluded there was nothing to suggest the road infrastructure played a part.

"The tragic incident that happened last July is still under investigation by the Coroner’s office and the HA are cooperating with the ongoing investigation. It would be inappropriate at this time to pre-empt any of its conclusions or recommendations."

Latest Issue

latest magazine issue

ALSO INSIDE:

  • Exclusive: M25 delays data doesn't add up
  • Autonomous vehicles: Life after the hype
View the latest issue


Highways jobs

Trainee Traffic Installation Technician

Competitive + Commercial Vehicle
If successful in this role you will learn to install traffic signals, including the installation of ancillary and associated equipment and highways systems. England, Cumbria, Carlisle
Recruiter: Telent

Head of Transport Strategy & Road Safety

£76,594 - £84,443 per annum
We have a unique opportunity for you to shape, influence and create a better future for Warwickshire Warwickshire
Recruiter: Warwickshire County Council

Transport Development Officer OCC615931

£35,745 - £38,223 per annum
You will support senior colleagues in providing the highways and transport input to strategic development proposals. Oxfordshire
Recruiter: Oxfordshire County Council

Technical Lead - Oxford Workplace Parking Levy OCC616196

£47,420 - £50,512 per annum
An exciting opportunity has arisen at Oxfordshire County Council to join the Central Team Oxfordshire
Recruiter: Oxfordshire County Council

Traffic Management Order

between ME12 £42,840 and ME15 £54,129 per annum
We are looking for a self-motivated individual with an eye for detail responsible for drafting and making traffic management orders Merton, London (Greater)
Recruiter: London Borough of Merton

Team Leader LGV Driver

£26,421.00 - £29,269.00, Grade 6, 37 hours, Permanent
An exciting opportunity exists in the Council’s Street Scene Services for a Team Leader LGV Driver Wakefield, West Yorkshire
Recruiter: Wakefield Council

Waste Recycling Operative

£24,294.00 - £25,979.00, Grade 5, 37 hours, Permanent
An opportunity exists in the Council’s Street Scene Services for a Waste Recycling Operative. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Recycling Centre Site Operatives

Up to £23344 per annum + Per Annum, Pro Rata if part time
Recycling Centre Site OperativesPermanent, Full Time£23,344 per annum (pro-rata for part time roles)Location
Recruiter: Essex County Council

Highway Asset and Development Manager

Grade N Scp 50 £59,031 to Scp 53 £62,076, plus car allowance
To be responsible for leading, developing and delivering an effective, efficient and safe Highway Asset Management Service Bolton, Greater Manchester
Recruiter: Bolton Council

Streetworks Compliance Officer

£33,945 - £34,834
This is an exciting opportunity to join a new Streetworks Team Cumbria
Recruiter: Westmorland and Furness Council

Administration Assistant

£24,294 – 25,979 pro rata
We have an opportunity for an enthusiastic and capable person. Accrington, Lancashire
Recruiter: Hyndburn Borough Council

Mechanic (LCV/LGV)

£32,076 - £33,945 Plus Tool Allowance
The successful applicant will inspect, service and repair a variety of vehicles (LCV/LGV) Accrington, Lancashire
Recruiter: Hyndburn Borough Council

Contract Officer BDR

Band H - Band J £33,024 - £43,421 (pay award pending)
We are looking for an enthusiastic, talented, motivated, and ambitious person to become the BDR Contract Officer. Rotherham, South Yorkshire
Recruiter: Rotherham Metropolitan Borough Council

Principal Transport Officer

£63,112 per annum
leading the capital’s largest new regeneration project. Brent Civic Centre (32 Engineers Way, Wembley, HA9 0FJ).
Recruiter: Old Oak and Park Royal Development Corporation

Highway Condition & Safety Inspection Officer - CMB982e

Grade 10, £33,945- £34,834 per annum
To undertake regular highways safety and condition inspections of the highways network Cumbria
Recruiter: Cumberland Council

Director of Open Spaces, Leisure & Culture

up to £133,569
Enfield is home to an increasingly diverse population we are investing in our places and people Enfield (London Borough), London (Greater)
Recruiter: Enfield London Borough Council

Director of Economy, Transport and Planning

Circa £140,000
Instantly recognised for our maritime heritage and the UK’s only Island city. Portsmouth, Hampshire
Recruiter: Portsmouth City Council

Bicester Garden Town Programme Manager

Grade M
Cherwell District Council
Recruiter: Cherwell District Council

Mechanical Engineer

£36,648 - £39,186 (pay award pending)
You will be required to maintain effective liaison with other professionals and key stakeholders Rotherham, South Yorkshire
Recruiter: Rotherham Metropolitan Borough Council

Driver - Northallerton - (IPT234)

£23,893 to £25,119 per annum pro rata
We also undertake registered Local Bus Services (transporting the public) and community transport journeys. Northallerton, North Yorkshire
Recruiter: North Yorkshire Council

Highways Presents

 


Latest Video