Birmingham City Council has tendered a contract for the creation of a £19m new cycle route on the A38 between Selly Oak and Longbridge.

The contract is set to run for two years from 31 March 2027 to 31 March 2029, with the successful supplier set to be responsible for the construction of 4.95 km of new segregated cycle infrastructure along the A38 corridor. Included in the work will be associated highway improvements, junction upgrades, pedestrian and cyclist crossings, traffic signal modifications and supporting infrastructure.

Those wishing to bid for the contract have until 28 November to enquire, with tenders then due for submission by 18 December.

Birmingham CC is hoping to announce the awarded company in March 2027. Construction is currently expected to start in April 2027, with the works completion currently expected in May 2029.

Full details of the contract and how to apply can be found here.