The Scottish Government has made a major push to tackle bus service disruption from roadworks, including updating the Code of Practice for the Co-ordination of Works in Roads, providing new conflict management elements to the roadworks register and even using AI and machine learning to help tackle the issue.

Two pure maths PhD candidates were placed with the Scottish Road Works Commissioner this summer and given ‘free rein' and full access to roadworks data currently available in the recently updated Scottish roadworks register to tackle ‘these fairly broad challenges' with whatever methods they deemed necessary.

Among other techniques, they used machine learning to predict the impact of roadworks and improve how the system then checks for conflicts.

The work is still at an early stage. When investigating if machine learning approaches could distinguish between situations with and without roadworks based on available traffic data, they found that the current information ‘didn't provide a sufficiently strong signal for those models to reliably identify or predict roadworks impacts,' Kevin Hamilton, the Scottish road works commissioner, revealed at Road Expo Scotland this week.

However, Mr Hamilton added that these results were based on data sources that have since been updated, and that ‘it's possible that those changes might be enough' to improve the results of this research.

The team were more successful in other areas, though, with the creation of a ‘graph-based traffic criticality model' based on the Glasgow road network.

By creating a model of the network, removing streets and recalculating journey times, they found they could ‘identify which parts of the network would be most critical and most susceptible'.

While Mr Hamilton noted that this is a technique that has been used previously, the quality and availability of modern data has simplified the task. There were also areas that the PhD candidates identified that they felt could be improved with better origin-destination data and the inclusion of bus delay data.

Bus data improvements

Mr Hamilton also discussed updates to the Code of Practice for the Co-ordination of Works in Roads, which address the impacts on bus services.

The enhancements made to the code of practice focused on integrating bus open data and the introduction of a bus conflict check:

‘For roads authorities,' Mr Hamilton explained, ‘there's now a greater expectation that bus service impact will be considered as part of the coordination process and there's a requirement to have effective liaison with bus operators'.

‘For utilities, there's an expectation that planned works take account of known bus routes and the service patterns, and where significant impacts are identified, organisations - both utilities and roads authorities - should consider whether there's anything that can be done in terms of alternative timings, revised traffic management, and obviously engagement with the affected stakeholders, including the bus companies themselves.'

‘The key message,' he added, ‘is that co-ordination should be proactive rather than reactive, and what promoters need to be able to demonstrate is that they have used their best endeavours in line with the legal duties.'

According to data now integrated into the roadworks register, around 40% of all roadworks are on or near bus routes, and with around 180,000 registered roadworks every year in Scotland (a near 40% increase on pre-COVID figures of 130,000), this can significantly delay bus services.

The issue is further compounded by the number of routes and services that can be impacted by a single worksite.

‘For example,' Mr Hamilton said, ‘when I had a look at the data for September, there were eight individual sets of roadworks that each affected over 100 different bus services. So, it's quite a significant impact that roadworks can have.'

To support these new requirements in the updated code, the roadworks register now includes new functionality ‘specifically designed' to improve the visibility of bus services and the impacts that works might have.

‘The first enhancement is the integration of bus stop and bus route data directly into the register, so the people who are planning works can now see what bus routes will be affected.'

This, Mr Hamilton said, will give the ‘earliest opportunity' for work planners to ensure they've considered those impacts on bus users.

‘As a development of this, we recently introduced specific conflict checking, which actively flags up locations where proposed works coincide with bus routes. For the first time, conflicts will be flagged where more than one set of works occurs on the same bus route, even if those works are in different local authority areas.'

The introduction of this additional data has allowed the Scottish Government to filter the information and provide ‘a targeted subset of all the data' directly to bus operators and other interested parties.

Mr Hamilton said: ‘Now that we know where the worst routes are and we know where the roadworks are, we can put the two things together and make it available. And we're doing this through publication of a new disruptions data feed.'

Provided by Traveline Scotland, the system is designed for daily use, with the route data displayed on the GIS layer. The route is shown along with the services, the frequencies and contact details for the bus operators.

Additionally, the system now detects conflicts between works and bus routes automatically, and where potential conflict exists, the system highlights it for consideration.

‘It doesn't mean the works can't proceed,' Mr Hamilton explains. ‘Instead, it acts as an early warning that allows road authorities and promoters to consider any mitigations. The latest development of this identifies where there's more than one works on an individual route.'