£125m bridge delayed, despite 'good progress'

24/08/2023
Chris Ames

Suffolk County Council has admitted that the Gull Wing bridge at Lake Lothing in Lowestoft will not open until next year.

The £125m bridge, which is funded with £73m from the Local Growth Fund and will provide a third crossing over Lake Lothing, was scheduled to open ‘Mid/Late 2023’.

The council said contractor Farrans has applied for an extension of the closure of Denmark Road to allow for the completion of the highways works on the northern side of Lake Lothing but that construction of the bridge itself ‘continues to make good progress’.

It said the bridge will open to the public in 2024 after installation of the main bascule span in the new year, ‘pending agreement with Associated British Ports’.

However, the website for the project gives the date for that element of the construction as ‘Early/Mid 2023’.

Seven of the bridge’s eight spans have been lifted into place, the concreting of the bridge deck slabs is well underway on both sides of Lake Lothing, and the new control room at the top of the control tower is under construction, the council said.

The plant room building is also currently being fitted out with the power supply, hydraulic pumps, communications equipment, and other building services.

The giant ‘J’ beams and bridge deck, which are currently being fabricated and assembled in Belgium and the Netherlands, will arrive by sea.

The council said that during installation and commissioning of the bascule span, ‘the final and most complex major element of this unique and challenging project’, the navigation channel is expected to close for three weeks.

This will be followed by a short period of time for final commissioning and for staff to be trained in the operating of the bridge before opening.

Project director Simon Bretherton said: ‘A clearer view of the timetable for its completion and opening will emerge as we undertake that final major component during a closure of the main navigation channel in the new year.’

He said the bridge would be ‘a complex and challenging infrastructure project at the best of times’, but that he would ‘say nothing’ of what he said were ‘the challenges of COVID and the global supply issues we have faced in the past few years’.

He added: ‘We will continue to work with our contractor, Farrans, to complete the remaining works as quickly as we can. Although there will continue to be some disruption in the short term, the long-term benefits of the new bridge will be felt for many decades to come.’

The road closure, which began on 1 March and was due to last ‘no longer than six months, is now expected to be in place until the end of October’.

The authority said the building of the new northern roundabout and approach road to the bridge, including new drainage, attenuation ponds, and utilities works, is taking longer than previously estimated.

Latest Issue

latest magazine issue

 

ALSO INSIDE:

  • Exclusive: Smart Motorways
  • Are you AI protected?
  • Traffex Parkex Evex Cold Comfort
View the latest issue


Highways jobs

Multi Skilled Operatrive x4

£22,737.00 - £29,269.00, Career grade 3-6, 37 hours, Permanent
We are seeking enthusiastic and capable colleagues to join our Highway Operations team that forms part of the Highway Network Management. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Supervising Technician

£33,024.00 - £35,745.00, Grade 8, 37 hours, Permanent
The purpose of this role is to support the Workshop Manager you will be required to work closely with other Supervising Technicians. Newton Bar Depot, Central Vehicle Workshops, Newton Bar, Wakefield WF1 2TU
Recruiter: Wakefield Council

Heavy Vehicle/Plant Apprenticeship

Age dependent (Under 18 yrs - £12,347, 18-20 yrs - £16,591, 21+yrs - £22,071)
The programme can start to build your career, or help you to re-train, becoming a valued, recognised and rewarded team member. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Senior Engineer - Highways and Drainage

£40,221 - £44,428 + 12% Attraction + Retention Payment equating to actual pay £45,047 - 49,759
This is an exciting opportunity to join us as a Senior Engineer. Lincolnshire
Recruiter: Lincolnshire County Council

Service Manager - Highways (Asset and Traffic)

£48,474 to £51,515
A vacancy has become available for a Service Manager to join and manage our successful Highways Assets and Traffic team. Torbay, Devon
Recruiter: SWISCo

Traffic Management Technician - WMF1090e

Salary £26,421 - £27.334
This is a role for Traffic Management Technician to be based in the Eden area. Penrith, Cumbria
Recruiter: Westmorland and Furness Council

Assistant Arboricultural Consultant

£26100 - £30706 per annum + + 26 Days Leave & Defined Benefit Pension
Assistant Arboricultural ConsultantPermanent, Full TimeUp to £30,706 per annumLocation
Recruiter: Essex County Council

Heavy Goods Vehicle Mechanic

£27,507 - £29,418
You will need to be suitably experienced, hold a minimum of an NVQ Level 2 (or equivalent). Derby
Recruiter: Derbyshire County Council

Principal Engineer - Highways Development Management

£48,378 - £51,571
You will play a lead role on all major highway development proposals across West Northampton. One Angel Square, Northampton
Recruiter: West Northamptonshire Council

Transport Planning & Data Manager - CMB1061e

£62,273 - £65,017
Cumberland Council is a dynamic and forward-thinking authority dedicated to enhancing public services Cumbria
Recruiter: Cumberland Council

Transport Planner (Area Travel Plans) OCC616326

£39,186 - £42,403 per annum
It doesn’t matter where you’ve been, or where you’re going, it’s about the journey. Oxfordshire
Recruiter: Oxfordshire County Council

2x Technical Lead (Area Travel Plans) OCC616320

£43,421 - £46,464 per annum
It doesn’t matter where you’ve been, or where you’re going, it’s about the journey. Oxfordshire
Recruiter: Oxfordshire County Council

Assistant Transport Planner OCC616317

£29,269 - £32,076 per annum
It doesn’t matter where you’ve been, or where you’re going, it’s about the journey. Oxfordshire
Recruiter: Oxfordshire County Council

Principal Engineer - Highways Development Management

£48,378 - £51,571
We are looking for an experienced and talented professional to join West Northampton Council as our Highways Development Principal Engineer. One Angel Square, Northampton
Recruiter: West Northamptonshire Council

Structural Highway Maintenance – Highway Engineer

£36,648 - £39,186 per annum
An exciting opportunity has arisen for a driven and self-motivated engineer to join our Structural Highway Maintenance Team. Warwickshire / Countywide
Recruiter: Warwickshire County Council

Highway Asset and Development Manager

Grade N Scp 50 £59,031 to Scp 53 £62,076, plus car allowance
To be responsible for leading, developing and delivering an effective, efficient and safe Highway Asset Management Service Bolton, Greater Manchester
Recruiter: Bolton Council

Highways Engineer

£37,336 - £39,186
Wiltshire Highways – Enhancing Lives, Building Communities Wiltshire
Recruiter: Wiltshire Council

Engineer

£40,221 - £51,515
As part of a friendly and enthusiastic team, you will play an important role in designing innovative urban transport and public realm projects 100 Temple Street Redcliff Bristol BS1 6AN
Recruiter: Bristol City Council

UGO Bus Driver

Up to £23344 per annum
UGO Bus DriverPermanent, Full Time and Part TimeUp to £23,344 per annum (FTE)Location
Recruiter: Essex County Council

Parking Finance and Debt Officer RBKC616576

£37,575 - £41,286 per annum
In Kensington and Chelsea, we put local people and local businesses at the heart of decision-making Kensington and Chelsea, London (Greater)
Recruiter: The Royal Borough of Kensington & Chelsea Council

Highways Presents

 


Latest Video