A259 works delayed as costs rise again

07/06/2021
Chris Ames

A major project to widen around 2km of single carriageway on the A259 in Angmering and Littlehampton to dual carriageway has been delayed by the COVID-19 crisis.

The scheme, which covers two single carriageway sections of the road, also faces a further cost increase.

West Sussex County Council told Highways that the pandemic had led to a need ‘to draw down on additional funding from Central Government, which was made available for this purpose’ but that a current anticipated cost was not currently available.

A visualisation of how the Olliver Acre junction at Littlehampton will look

The scheme has already seen a significant increase in cost, up £10.5m from an initial budget of £15.3m to a new budget, approved in June 2019, of £25.8m, including a risk element priced at approximately £1.5m.

The council said that while ‘progress continues to be made’ on the project, it is now forecast to be completed in the winter of 2022, rather than the autumn.

Site preparation, including vegetation clearance at the Angmering end of the scheme, was carried out in early in 2019. Further site clearance and Archaeological investigation work took place throughout August 2020.

The council said these works, as well as drainage works and preparatory earthworks works, had progressed well since, with main construction works beginning in September 2020, and utility companies had also been busy diverting their equipment to make room for the road widening.

However, progress has now slowed, particularly at the Angmering end of the scheme mainly because UK Power Networks is required to remove and replace a high-voltage electricity cable – ‘a substantial piece of infrastructure’ – at a cost of around £2m.

‘However, during the Covid-19 crisis, UK Power Networks had to refocus its workforce to deal with the national emergency and work related to the pandemic, such as getting supplies to testing centres, Nightingale hospitals and so on.’

A spokesperson said: ‘This unprecedented situation meant, understandably, they could not meet the demands of our programme.

‘However, we have actively been working with UK Power Networks and our principal contractor, Volker Fitzpatrick, in re-planning the works to try to reduce the impact of this problem. By working together, we have been able to reduce the delay to four months, resulting in a revised estimated completion in the winter of 2022.’

A spokesperson for UK Power Networks said: ‘We share the council’s desire for this project to progress quickly and continue to work closely with our customer to complete this work as quickly as possible.

‘We have appointed two contractors to accelerate our work and aim to complete the essential work on the cable diversion in September 2021. We plan to complete the remaining work after this, but this should not have any further impact on the construction of the dual carriageway.’

On Monday, the Department for Transport announced that it was providing £12m for the nearby Lyminster Bypass, a nearby £22m West Sussex CC scheme.

Highways jobs

Business Support Officer - Catering

£19,312 - £19,698 per annum
This job is Temporary for up to 12 months to cover operational needs. Kirklees, West Yorkshire
Recruiter: Kirklees Metropolitan Council

Road Safety & Sustainable Transport Assistant (Casual)

£11.73 - £12.69
Are you passionate about active travel with a particular interest in cycling? Telford, Shropshire
Recruiter: Telford & Wrekin Council

Street Works Inspector

£30,451 - £32,234 per annum
Are you passionate about highways and work planning? Telford, Shropshire
Recruiter: Telford & Wrekin Council

Commercial Transport Coordinator

£31,869 to £38,616 per annum
Are you passionate about making improvements and implementing change? London (Greater)
Recruiter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Ugobus Driver

Up to £19579 per annum
Ugobus DriverPermanent, Part TimeUp to £19,579 per annum (full time equivalent)Location
Recruiter: Essex County Council

Senior Procurement Manager x3

£51000 - £60500 per annum + + Flexible Working & Local Gov Pension
Category and Supplier Relationship Specialists x3Fixed Term, Full TimeUp to £60,609 per annumLocation
Recruiter: Essex County Council

Senior infrastructure engineer

£45.834 - £56.141
You’ll lead the building, testing and monitoring new and existing services both on-prem and in the cloud. Greenwich, London (Greater)
Recruiter: Royal Borough of Greenwich

Infrastructure engineer

£37.772 - £46.999
This is a great role in a vibrant and growing team; we’re looking for people who have some experience in infrastructure engineering... Greenwich, London (Greater)
Recruiter: Royal Borough of Greenwich

Category and Supplier Relationship Specialist

£52000 - £60609 per annum + + Flexible Working & Local Gov Pension
Category and Supplier Relationship SpecialistPermanent, Full TimeUp to £60,609 per annumLocation
Recruiter: Essex County Council

School Crossing Patroller

£4,657
Are you looking for a rewarding job helping the community? London (Greater)
Recruiter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Local Plan Transport Advisor

£44,700 - £48,854
Do you have experience as a Transport Planner or Project Manager? East Sussex
Recruiter: East Sussex County Council

Lead Transport Modeller

£39,713 - £43,397
Do you have experience as a Transport Modeller? Lewes, East Sussex
Recruiter: East Sussex County Council

Social Value Assistant Manager (mainly home based)

£33000 - £38000 per annum + + Flexible Working & Local Gov Pension
Social Value Assistant Manager (mainly home based)Fixed Term, Full TimeUp to £38,001 per annumLocation
Recruiter: Essex County Council

Traffic Projects Officer

£27,614 to £30,602 pro rata per annum
We have a great opportunity for a Projects Officer to join our busy Traffic Team. York, North Yorkshire
Recruiter: City of York Council

Emergency Planning Assistant

£28,452 - £37,026 depending on skills,
Are you interested in emergency planning and keen to be part of a supportive team? Sandwell, West Midlands
Recruiter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Network Management Officer

£22,183 - £32,234
This is a varied role for an enthusiastic and motivated candidate, with experience of highway maintenance or a technical background, who... Cambridgeshire
Recruiter: Cambridgeshire County Council

Environmental Health Officer

£32,910 - £35,745
Reporting to the Public Protection Manager, (Health, Food& Safety) the duties that the post holder is responsible for include... Telford, Shropshire
Recruiter: Telford & Wrekin Council

Environmental Health Officer

£32,910 - £35,745 per annum
Reporting to the Public Protection Manager, (Health, Food& Safety) the duties that the post holder is responsible for include... Telford, Shropshire
Recruiter: Telford & Wrekin Council

Local Highway Officer

£22,183 - £32,234
The role is to identify maintenance repairs and improvements and to work with Community Groups and Partners, dealing with... Cambridgeshire
Recruiter: Cambridgeshire County Council

Technical Business Analyst (Highways)

Up to £46359 per annum
Technical Business Analyst (Highways)Permanent, Full TimeUp to £46,359 per annumLocation
Recruiter: Essex County Council

Highways Presents

Highways on Fridays

Register now!

Latest Issue

latest magazine issue

INSIDE:

  • The Queen's Speech and procurement reform
  • The remarkable benefits of controlled motorways
View the latest issue

Latest Video