Amey loses Birmingham battle in Appeal Court

23/02/2018 |

The Court of Appeal has found in favour of Birmingham City Council and against Amey in a long running and occasionally bitter highways dispute, rejecting the company’s ‘ingenious new interpretation of the contract’.



Amey was contracted in 2010 to carry out a 25 year PFI contract for the city, and ‘all went well for the first three and a half years’ the Court reports.


However the partners fell out from 2014 onwards when it became clear the firm was not carrying out basic works the council felt it was obliged to do.


In a sign of how complex and bitter the dispute became, the Appeal Court documents refer to a 30-hour exchange of notes after one hearing ‘before the gunfire died down’.


Amey Birmingham Highways Ltd (ABHL) was ‘deliberately leaving the defects in selected areas untreated’ the court found and had ‘been carrying out works based on inaccurate inventory information’.


The firm argued that certain sections of the contractual inventory data, which established the nature and condition of the network under its care, did not have to be updated under the letter of its contract and therefore had stopped updates to a computer system known as the Project Network Model (PNM).


The court found: ‘Clause 5 of the contract required ABHL to satisfy themselves about the extent of the project network. That requirement only makes sense if ABHL were required to maintain the roads, footways, verges, kerbs and cycle tracks which actually existed.


‘If ABHL were going to work for the next 25 years on the original unamended inventory in the PNM, there would be no point in satisfying themselves about the extent of the project network which actually existed.’


The Court of Appeal reinstated judgements from a previous independent adjudicator in the case, whose decision Amey had initially overturned by a High Court Judgement in 2016.


The Court of Appeal made declarations ‘to the same effect as the declarations made by the adjudicator’, namely:


(i) That ABHL’s obligations to perform the Core Investment Works and meet the requirements of Performance Standard 1 extend to the Project Network as a whole and are not limited to the RSLs as recorded in the Project Network Model contained in DRD0626 [ the initial version of Project Network Model].


(ii) That ABHL must update the Project Network Model and maintain a Project Network Inventory which accurately reflects the actual extent of the Project Network and the Project Road.


(iii) That the Certificates of Completion for Milestones 6 to 9 inclusive be set aside, alternatively opened up, reviewed and revised and the relevant calculations performed again by reference to the actual Project Network Inventory.”


The judgement is also notable for the way it addresses the spirit as well as the letter of such long-term local government ‘relational contracts’. Lord Justice Jackson noted: ‘Any relational contract of this character is likely to be of massive length, containing many infelicities and oddities. Both parties should adopt a reasonable approach in accordance with what is obviously the long-term purpose of the contract. They should not be latching onto the infelicities and oddities, in order to disrupt the project and maximise their own gain.’


Cllr Stewart Stacey, Birmingham’s cabinet member for transport and roads, said: ‘This is a significant step for the council in our aim of getting the level of investment into our roads that we believe should have been provided by Amey during the first five years of the contract. It fully justifies our decision to appeal the High Court judgement from 2016 and we now need to move forward in light of the Appeal Court ruling in getting the condition of our roads and footways to the standard that the people of Birmingham expect and deserve.’


An Amey spokesperson said: ‘In 2010 Amey embarked on a 25-year highways contract with Birmingham City Council. Since then, we have delivered significant investment in the city’s roads, which has seen considerable improvements to the network.


‘We have resurfaced 500 miles of carriageway – over one-third of Birmingham’s roads – and over 400 miles of pedestrian footway. We’ve also replaced 42,000 street lights, and over half of the city’s traffic signal systems. Amey has made a significant investment to upgrade the road network in and around Birmingham. We have completed a comprehensive programme of investment as part of a major infrastructure initiative, and it is one of the most capital intensive projects in Europe.


‘We have been involved in a dispute with Birmingham City Council over the last 24 months regarding the scope of our contractual obligations in the core investment period. Unfortunately, despite the High Court having found in our favour previously the ruling was overturned by an appeal.


‘Amey is disappointed at the outcome of the case, and has been preparing for all outcomes. We are currently considering all options for next steps. We remain committed to the market and all our clients. The issues raised in this dispute were very specific to the contract and its structure.’

Highways InProfile

latest magazine issue
Highways jobs

Head of Highways Contracts & Network

£81,803 progressing to £90,664 per annum
This role is fundamental to the success of the Highways Service. Hertfordshire
Recruiter: Hertfordshire County Council

Senior Civil Engineer - Major Projects x 4

£45,894.00 - £54,952.00
We are looking for experienced engineers to help us progress a number of key projects and programmes Glasgow, Glasgow City
Recruiter: Transport Scotland

Technician - Maintenance

£31001.0000 - £36471.0000 per annum
Essex Highways is responsible for managing and maintaining one of the largest highway networks in the country
Recruiter: Essex County Council

Highways Contract Engineer

£46,731 - £49,764
The team helps provide a safe road network that operates efficiently and effectively.  Northamptonshire
Recruiter: North Northamptonshire Council

Principal Transport Planner

£46,731 - £49,764 (pro-rata)
We are looking for an experienced professional to join us on a six-month temporary contact as a Principal Transport Planner. Kettering, Northamptonshire
Recruiter: North Northamptonshire Council

Highways Maintenance Operative

£Competitive
We have a fantastic opportunity for a Permanent Highways Maintenance Operative Broughton, Brigg
Recruiter: Amey

Head of Highways Contracts & Network

£81,803 progressing to £90,664 per annum
The team includes approximately 60 directly employed HCC people Hertfordshire
Recruiter: Hertfordshire County Council

Principal Construction Manager

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Principal Construction Manager Yorkshire and the Humber
Recruiter: Amey

Quality Technician

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Quality Technician Yorkshire and the Humber
Recruiter: Amey

Senior Highway Engineer (Development Management)

£42679.0000 - £50211.0000 per annum
Senior Highway Engineer (Development Management)Permanent, Full Time£43,960 to £51,718 per annum*Location
Recruiter: Essex County Council

Project Manager (Major Projects)

£44,711 - £47,754
Are you an experienced project professional or engineer with looking to take the next step in your career? Halifax, West Yorkshire
Recruiter: Calderdale Metropolitan Borough Council

Senior Civil Engineer - Roads

£45,894 - £54,952
Are you an experienced engineer looking to support the Scottish Government’s national objectives. Scotland
Recruiter: Transport Scotland

Project Team Manager

£55,147 to £60,676 per annum
We are pleased to be able to offer an opportunity for a role as Design Team Manager Norwich, Norfolk
Recruiter: Norfolk County Council

Clerk of Works

GRADE 08 (£37,938 - £41,511)
Warrington is one of the most successful towns in the country Warrington, Cheshire
Recruiter: Warrington Borough Council

Assistant Projects Engineer

GRADE 06 (£29,093 - £32,654),GRADE 07 (£33,366 - £37,035), GRADE 08 (£37,938 - £41,511)
Warrington is one of the most successful towns in the country Warrington, Cheshire
Recruiter: Warrington Borough Council

Principal Engineer - Traffic Management

£45,718 - £48,710 per annum
At Bath & North East Somerset Council we have one overriding purpose – to improve people’s lives. Bath, Somerset
Recruiter: Bath & North East Somerset Council

Vehicle Technician - Improver

£28,624 - £30,060
Transport Services is responsible for all aspects of transport and related services Huddersfield, West Yorkshire
Recruiter: Kirklees Metropolitan Council

Programme Delivery Office Administrator

Grade 9 £31,344 - £33,253 per annum
At Derbyshire, we have been on a journey to transform the way we deliver highway services to make them fit for the future Derbyshire
Recruiter: Derbyshire County Council

Support Officer - Highways Asset Management Systems

£31,586 - £34,314
We are a forward-thinking organisation dedicated to maintaining and improving our highway infrastructure. Lincolnshire
Recruiter: Lincolnshire County Council

Principal Transport Planner (Strategy)

£46,731-£49,764
We are looking for an experienced professional to join North Northamptonshire Council as a Principal Transport Planner (Strategy). Sheerness House, 41 Meadow Road, Kettering moving to Haylock House, Kettering Parkway, Kettering NN15 6EY, United Kingdom
Recruiter: North Northamptonshire Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW