The long legal read: Filling the funding hole

18/09/2019

Ava Zadkhorvash and Jon Hart of award winning law firm Pinsent Masons LLP take a look at potential funding models for highways infrastructure, Regulated Asset Bases and life after PFI and PF2.

Spare a thought for our Treasury civil servants and policy makers. Every now and again, they may be reminded of a time when they turned up for work and the key issue of the day was not Brexit.

Outside the hurly-burly of deal/no-deal, rogues and proroguing, from time to time, other imperatives occasionally rise to the surface, including coming to terms with the state of the UK's infrastructure and how it is going to be paid for.

According to various sources, more than £600bn is due to be invested in infrastructure over the next 10 years, with the Government deciding that around half of the planned investment should come from the private sector. So far, so staggering.

However, there are some gaps in the picture as to what role the private sector may be required to play and how.

The end of PFI?

Less than 12 months ago, a previous chancellor called time on the PFI and PF2 model, particularly the use of the design-build-operate and maintain structure (DBFOM). Under DBFOM, a single consortium would be appointed under a long-term (typically 25 to 30 years) contract, to build a new asset using private debt, and then to operate and maintain it.

The majority of construction risks would be borne by the consortium, flowed down to a design and build contractor, which sometimes would also be an investor in the consortium.

Operational risks would be borne by an O&M contractor and levels of payment to be made by the public sector would be geared to how well the asset performed in practice, measured by a complex contractual mechanism which, depending on individual contracts, would take account of factors such as lane closures, journey times and safety performance.

In a very limited number of cases, the model is adapted to provide that payments to a consortium will be made from a revenue stream (for example tolls) on a ‘concession’ or ‘demand risk’ basis.

DBFOM and its variants lay at the heart of PFI and PF2. In its time, it has been used to build hospitals, schools and housing. In the highways sector, it has been perhaps less widely adopted, but has been used to deliver schemes such as the A1 Darrington-Dishforth scheme and the M25 road widening for the Highways Agency, as was.

There have also been a few examples of concessions – notably the M6 Toll Road. Certain local authorities have used this model for delivery of streetlighting schemes and highway maintenance.

This model and its contractual risk allocation have not been without controversy. On the one hand, there are the examples of Carillion's liquidation, the Aberdeen bypass and Birmingham Highways, which have seen contractors seriously affected by costs and deductions. On the other hand, there have been criticisms from think tanks such as the recent IPPR report into hospitals that there has been poor risk transfer and value for money for the public sector.

As readers will be aware, in the roads sector, Highways England was in the process of procuring two schemes using DBFOM at the time of last October's announcement - the A303 Stonehenge tunnel (above) and the roads for the Lower Thames Crossing (below). For potential tenderers and investors (some of whom had been tracking the projects for a considerable time) DBFOM's demise came as a bolt from the blue.

That said, the Treasury indicated at the time that it was open to looking at ‘other approaches’ for investing in infrastructure, including roads.

In this context, it is also important to mention that the chancellor's pronouncements are limited primarily to England. Both Wales and Scotland are continuing to develop their own project finance solutions, which are similar to DBFOM.

In Scotland, both the M8 and Aberdeen bypass projects have been procured using the ‘Not For Profit Distribution’ Model (NPDM), while the A465 Head of the Valleys scheme is being procured by the Welsh Government's ‘Mutual Investment Model’ (MIM). Both of these models require a successful consortium to provide design, construction and O&M services with the provision of private finance.

Where next?

So where are we now, 12 months later? In the first instance, there is opportunity to consider dispensing with any form of private finance involvement at all. Apparently the Stonehenge project will now be procured following a more traditional engineering procurement route, making use of the tried-and-tested (and usually heavily amended) NEC Engineering and Construction Contract.

As a procurement approach, this is relatively familiar territory, albeit that it lacks one of the often-overlooked benefits of the DBFOM model, of contractually addressing design and construction issues at the same time as long-term lifecycle and maintenance arrangements.

Perhaps as pertinently, from an investment perspective, consideration would need to be given as to whether this kind of approach may be adapted to provide for the use of external private finance – and if so how.

The scrapping of PFI and PF2 has been accompanied by a range of consultations sponsored by the Treasury. The Infrastructure Finance Review published earlier this year looked at the various private financing models already in use and how these ‘could be applied in new contexts’, in a bid to improve the public sector balance sheet, and ensure value for money for the taxpayer.

Regulated Asset Base

The Scottish NPDM and Welsh MIM do not appear to be given particularly extensive consideration, but one alternative, well-established, model being increasingly considered by the Government is the Regulated Asset Base (RAB).

RAB accounted for over £160bn of private sector infrastructure investments in 2018, particularly in the water, gas, electricity, telecoms, (and with some tweaks to the model) railways sectors. There has been a lot of interest in the Government's latest consultation, to see if RAB can be applied to the development of new nuclear power stations post-Hinckley C.

In simple terms, RAB uses the following structure:

  • an economic regulator grants a licence (rather than a DBFOM contract or concession issued by a governmental authority) to a private company to operate and maintain an infrastructure asset, providing the company the right to charge a regulated price to users
  • the economic regulator is an independent regulator appointed by statute that will set the price and will hold the company to account, ensuring that end-users are not exploited
  • demand risk is passed to the company as it charges the end-users of the product or service (e.g. users of water utilities)
  • the company agrees to invest certain sums in maintaining and developing the asset by reference to agreed ‘control periods’ – the regulator will look at the value of the underlying asset and will also set the weight average cost of capital (and from this the returns that the company might be making)

And how would this model work with the highways sector? Interestingly, although it was not implemented, in 2013 a consultation was launched to introduce the RAB model to the roads sector.

The proposed model suggested that the Government would initially portion for a user charge within motor taxes in order to help fund the operation and maintenance of the roads network. This would then be outsourced to the private sector, thereby, taking the project off-balance sheet from the public purse.

At the time, the CBI expressed concerns that this type of funding would not be sufficient to meet or cover the future investment needs and warned that the use of toll roads would likely have to be introduced.

Currently, the Office of Rail and Road (ORR) operates in a regulatory capacity in relation to Highways England and the strategic road network (SRN). As the ‘Highways Monitor’, the ORR enjoys certain enforcement powers to require that Highways England complies with Highways England's statutory licences and road investment strategy (analogous to the control periods mentioned above under a RAB) for the SRN.

The missing element here is, of course, the absence of an ‘end user’ in the same way that is the case for, say water utilities: something that was highlighted at the time of the 2013 consultation. Funding for the road investment strategy has been ring-fenced by the Department for Transport (and Treasury). 

While the technology for road user charging continues to develop (and certain optimists may say will provide a solution to the difficulties associated with the Brexit backstop for the Northern Ireland border), there is (obviously) no appetite yet for further developing the regulatory model to bring the highways sector closer to a pure RAB. Indeed, given the criticisms that have been levelled against asset holders in the electricity and water sector, some may argue that the likelihood of an RAB model for roads is further away than ever.

And yet… the question of investment remains and when or if the smoke of Brexit clears some of the affected civil servants may be able to get back to their day job of coming up with some possible solutions.

The National Infrastructure Commission (NIC) recently refined its analytical tool in a bid to ensure that the Government considers broader factors such as whole-life and social impact in their infrastructure procurement models.

Based on five road schemes, the pilot trial was inconclusive. It was not possible, nor realistic to evaluate the relevant costs and benefits of private financing and procurement methods traditionally used.

However, Sir NIC chair John Armitt said that: ‘transforming the nation's infrastructure means mobilising private sector investment alongside that of government’.

STOP PRESS: In last month's column, we highlighted the proposed changes to VAT invoicing – the so-called reverse charging – which would potentially have had a significant impact for both main contractors and subcontractors. The Government has listened to concerns from industry and is postponing the reverse charge to 1 October 2020. This will avoid the changes potentially coinciding with Brexit and will give businesses longer to prepare.

There were concerns that SMEs in particular were ill-prepared for the changes. This still means that the issues highlighted about considering changes to subcontracting arrangements and invoicing systems remain a source of legitimate concern – but now there is going to be a longer period of time to raise awareness and be ready for implementation.

Latest Issue

latest magazine issue

ALSO INSIDE:

  • Exclusive: M25 delays data doesn't add up
  • Autonomous vehicles: Life after the hype
View the latest issue


Highways jobs

Highway Condition & Safety Inspection Officer - CMB982e

Grade 10, £33,945- £34,834 per annum
To undertake regular highways safety and condition inspections of the highways network Cumbria
Recruiter: Cumberland Council

Director of Open Spaces, Leisure & Culture

up to £133,569
Enfield is home to an increasingly diverse population we are investing in our places and people Enfield (London Borough), London (Greater)
Recruiter: Enfield London Borough Council

Director of Economy, Transport and Planning

Circa £140,000
Instantly recognised for our maritime heritage and the UK’s only Island city. Portsmouth, Hampshire
Recruiter: Portsmouth City Council

Bicester Garden Town Programme Manager

Grade M
Cherwell District Council
Recruiter: Cherwell District Council

Mechanical Engineer

£36,648 - £39,186 (pay award pending)
You will be required to maintain effective liaison with other professionals and key stakeholders Rotherham, South Yorkshire
Recruiter: Rotherham Metropolitan Borough Council

Driver - Northallerton - (IPT234)

£23,893 to £25,119 per annum pro rata
We also undertake registered Local Bus Services (transporting the public) and community transport journeys. Northallerton, North Yorkshire
Recruiter: North Yorkshire Council

Senior Fleet Compliance Assistant

£26,873-£29,269 per annum
We’re looking for a Senior Fleet Compliance Assistant to join our Fleet Management Team. Skipton, North Yorkshire
Recruiter: North Yorkshire Council

Senior Officer (Traffic and Road Safety) OCC615318

£43,421 - £46,464 per annum
Please note we are actively looking at our ways of working using everything we have learnt and heard from our employees Kidlington, Oxfordshire
Recruiter: Oxfordshire County Council

Senior Officer (Traffic Control) OCC613685

£35,745 - £38,223 per annum
You will take a lead role in creating and implementing traffic signal and information strategies Kidlington, Oxfordshire
Recruiter: Oxfordshire County Council

Officer Traffic Control Centre OCC609561

£29,269 - £32,076 per annum
This role in our team supports the movement of traffic across Oxfordshire by responding to both planned and unplanned events. Kidlington, Oxfordshire
Recruiter: Oxfordshire County Council

Programme Control Officer

£35,745 - £36,648
The ideal candidate will have experience of project or programme management techniques and methodologies. Cumbria / Various
Recruiter: Cumberland Council

Senior NEC4 Contract Supervisor CMB1000e

£44,428 – £45,441
Are you an experienced NEC4 Supervisor? Cumbria
Recruiter: Cumberland Council

Major Projects NEC4 Senior SupervisorCMB999e

£53,775 – £55,963
Are you a knowledgeable or accredited NEC4 Supervisor? Cumbria
Recruiter: Cumberland Council

Driver/Loader (Waste Services)

Grade 6 Level 1 - 4 (£26,224 to £28,725 per annum)
Do you want a rewarding role, working outdoors, as part of a committed and hardworking team? York, North Yorkshire
Recruiter: City of York Council

Senior Highways Engineer (Highway Design)

£43,421- £46,464 per annum
The Highway Design and Regulation Team is integral to preserving the integrity and functionality of our highway infrastructure Princess Buildings, Halifax,
Recruiter: Calderdale Metropolitan Borough Council

Senior Capital Engineer

£43,421- £46,464 per annum
The Highway Capital Maintenance Team is integral to preserving the integrity and functionality of our highway infrastructure Princess Buildings, Halifax,
Recruiter: Calderdale Metropolitan Borough Council

Student Placement Engineer Transportation Infrastructure Service

£23,383 per annum (pay award pending)
You'll complete a series of placements, in different teams. Rotherham, South Yorkshire
Recruiter: Rotherham Metropolitan Borough Council

Workshop Shift Supervisor - Engine Shed Lane - (094739)

£35,745 - £40,221
North Yorkshire Council operates a fleet of about 960 vehicles across North Yorkshire. Skipton, North Yorkshire
Recruiter: North Yorkshire Council

Assistant Technician / Technician / Senior Technician

£25,119 - £33,024
Lincs Laboratory is UKAS accredited to BS EN ISO/IEC 17025 for construction materials sampling and testing Lincoln, Lincolnshire
Recruiter: Lincolnshire County Council

Operations Technician (Career Grade)

£22,737 - £30,296
Lincs Laboratory is a specialist in-house service of the Highways Services of Lincolnshire County Council. Lincoln, Lincolnshire
Recruiter: Lincolnshire County Council

Highways Presents

 


Latest Video