Planned closures avoided as M54 works completed early

16/05/2025 | GEORGE BARKER

Planned closures avoided as M54 works completed early

National Highways has completed essential repairs, which began this February, to a concrete section of the M54, meaning that two scheduled weekend closures are no longer needed.

Eight full weekend closures were originally scheduled – including over the Easter bank holiday weekend – to allow for the works to take place between junctions 2 and 4, but National Highways said that the contractors had made ‘swift progress’ and were able to complete the work using only six of the closures, and without impacting on the bank holiday.

Concrete roads, which were built primarily in the 1960s and 70s, make up roughly 400 miles (4%) of England’s strategic road network. The concrete slabs they are comprised of are more durable than asphalt, but after multiple decades of use, they are now nearing the end of their lifespan and need specialist repairs to ensure their continued use.

National Highways project manager Dan Bothwick said: ‘We always try to minimise disruption wherever possible and only close the road if we really have to, for the safety of both our workforce and road users.

‘So we are delighted that we have been able to reduce the number of weekend closures, and the impact on road users, and that we could finish off some works overnight when we know roads are quieter.

‘In fact, we actually carried out more repairs than anticipated as we discovered additional areas of the carriageway that needed attention once the scheme got under way. Drivers can now enjoy smoother, and safer, journeys along the M54.’

Highways manager Adrian Pike from contractor Concrete Repairs Limited (CRL), which headed up the project, said: ‘CRL were involved in the scheme several months before the works began and carried out detailed Early Contractor involvement (ECI). This really helped with the planning, sequencing and methodology particularly regarding the traffic management and phasing/resourcing of each activity.

‘We employed a public liaison officer who helped to ensure that whilst disruption was inevitable over the weekends, information about the works and diversion routes was given at an early stage.

‘The team worked really well and it is a credit to all those involved that the scheme completed ahead of schedule minimising the impact to the travelling public, local businesses and other stakeholders.’

Highways InProfile

latest magazine issue
Highways jobs

Development Engineer

£35,967 - £41,268 per annum
Are you ready to play a key role in shaping and safeguarding the future of our highways and public spaces? Bexley (City/Town), London (Greater)
Recruiter: London Borough of Bexley

Professional Services Partnering Manager

Grade 13 £47,653 - £51,296 per annum (pay award pending)
We are seeking a dynamic and experienced Professional Services Partnering Manager to lead the strategic management Darley Dale, Matlock
Recruiter: Derbyshire County Council

Technical Supervision Manager

Grade 13 £47,653 - £51,296 per annum (pay award pending)
We are looking for an experienced and driven Technical Supervision Manager to lead our technical supervision teams within the Highways Service. Derbyshire
Recruiter: Derbyshire County Council

Street Lighting Electrician (CDC)

Grade 8, £32,662 - £36,239 (pay award pending)
Highways Operations is a growing service area within the Place directorate. Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Highways Assistant Engineer WMF2133e

£39,513 to £40,476
We have an exciting opportunity for the right person to work within the challenging and ever-changing landscape. Penrith, Cumbria
Recruiter: Westmorland and Furness Council

Highways Inspector/NRSWA

£36,345 - £40,344
We are looking for an organised and self-motivated individual to join our Streetworks Team based in Hackney Central. Hackney, London (Greater)
Recruiter: London Borough of Hackney Council

Structures Commissioner

Grade 14 £53,166 - £59,080 per annum (Pay Award Pending)
We are seeking an experienced and strategic leader to join our team as the Structures Commissioner. Derbyshire
Recruiter: Derbyshire County Council

Team Leader Network Co-ordination

£51,429 - £58,140
As Team Leader for Network Coordination, you’ll manage a team that oversees all works and events on our public highways. Kensington and Chelsea, London (Greater)
Recruiter: The Royal Borough of Kensington & Chelsea Council

PRINCIPAL TRANSPORT PLANNING OFFICER

£43693 - £46731
We have an exciting opportunity for an experienced professional to join our team in Hull as a Principal Transport Planning Officer. Kingston upon Hull, East Riding of Yorkshire
Recruiter: Hull City Council

HIGHWAYS AND TRAFFIC ENGINEER - 4 POSTS

£43693 - £46731
We have several exciting opportunities for suitably qualified Highways Civil Engineers and Traffic Engineers Wilson Centre, 1st floor, Hull HU1 2AG
Recruiter: Hull City Council

Principal Transport Planner

£45,718 to £49,764
Do you have considerable experience in the transport strategy and policy, and are you looking for your next career development opportunity? Sheffield, South Yorkshire
Recruiter: Sheffield City Council

Project Lead - Bridges and Structures WMF3037e

£45,718 to £46,731
We are currently seeking to recruit a Project Lead to join our Bridges and Structures team Kendal, Cumbria
Recruiter: Westmorland and Furness Council

Highway Network Technician - WMF2090e

£27,711 - £28,624
We are looking to recruit a friendly and motivated candidate to join our Highways Maintenance Team as Highways Network Technician. Kendal, Cumbria
Recruiter: Westmorland and Furness Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW