M4 relief road plans dropped

04/06/2019 | DOMINIC BROWNE

First Minister Mark Drakeford has abandoned plans for an M4 relief road on cost and environmental grounds, stating there is 'no prospect of the project being implemented in the foreseeable future'.

In a decision letter he wrote:'[The] Cabinet concluded that, in light of the cost of the Project, other demands and potential demands on the Welsh Government’s capital budget, and uncertainty as to the financial position of the Welsh Government, the cost of the Project, and its consequential impact on other capital investment priorities, was not acceptable.

'Accordingly, the Welsh Government’s position is that it will not provide funding for the Project. For the avoidance of doubt, the position adopted by the Cabinet does not call into question the Inspector’s conclusion that the Project would constitute at least sound value for money, and in all probability good value for money, as this was not an issue considered by the Cabinet.

He added: 'I recognise the Inspector’s conclusions as to the advantages and disadvantages of the Project. However, I attach greater weight than the Inspector did to the adverse impacts that the Project would have on the environment.'

'In particular, I attach very significant weight to the fact that the Project would have a substantial adverse impact on the Gwent Levels SSSIs and their reen network and wildlife, and on other species, and a permanent adverse impact on the historic landscape of the Gwent Levels.'

The Government's preferred Black route for the scheme would have taken the road through these sensitive wetlands.

The first minister concluded: 'In my judgement the Project’s adverse impacts on the environment (taken together with its other disadvantages) outweigh its advantages.'

The project has already been subject to a two-year delay and a cost rise of £136m to mitigate the road’s impact on nearby port operations (pictured).

After the Welsh Government declared a climate emergency recently it seemed the political tide was turning against the controversial scheme.

The proposed relief road was opposed by environmentalists; however it was supported from the CBI and the UK Government.

In 2017, Welsh Government economist Stephen Bussell, who carried out economic appraisals of the project, stated that when wider impacts are included, the Net Present Value of the scheme was £1.17bn with a Benefit Cost Ratio of 2.22.

This was based on economic benefits of £2.12bn against a cost of £952m.

However, Bridget Fox, sustainable transport campaigner at Campaign for Better Transport, said: ‘The M4 Black Route would be a disaster for nature, climate and public health. This road was first conceived of 25 years ago and we now know that building more roads does not address the problem of congestion, it only make it worse.'

She said the inquiry ‘needs to look at genuine alternatives including rail freight and public transport options to get unnecessary journeys off the roads and reduce congestion’.

Highways InProfile

latest magazine issue
Highways jobs

Highways Maintenance Manager

£49,764 - £53,817 per annum
We are looking for an experienced co-ordinator to join the team as a Highways Maintenance Manager Skipton, North Yorkshire
Recruiter: North Yorkshire Council

Civil Enforcement Officer

£25,183 - £26,409
Are you looking for a role that allows you to earn whilst been outdoors across the district of North Yorkshire? Whitby, North Yorkshire
Recruiter: North Yorkshire Council

Civil Enforcement Officer

£25,183 - £26,409
Are you looking for a role that allows you to earn whilst been outdoors across the district of North Yorkshire? Northallerton, North Yorkshire
Recruiter: North Yorkshire Council

Senior Street Cleansing Technician (CDC)

Grade 6, £25,175 - £25,983 (Pay award pending) + 6% AIA
We are about to embark on an ambitious programme of change in our city centre Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Highways Improvement Manager

£49,764 - £53,817 per annum
Would you like to be part of our friendly, supportive, Highways team? Scarborough, North Yorkshire
Recruiter: North Yorkshire Council

Highways Delivery Manager

£69,123 - £72,783
This is an exciting role leading maintenance and construction delivery. Northumberland
Recruiter: Northumberland County Council

UGO Bus Driver

Up to £25081.00 per annum
UGO Bus DriverPermanent, Part TimeUp to £25,081 per annum (full time equivalent)Location
Recruiter: Essex County Council

Street Scene Workforce Support Officer

£27,711.00 - £30,559.00, Grade 6, 37 hours, Permanent
An opportunity exists in the Council’s Street Scene Services for a Street Scene Workforce Support Officer Wakefield, West Yorkshire
Recruiter: Wakefield Council

Highways Officer

£33,366 - £37,035 per annum
We are seeking to recruit a Highways Officer based at our Highways Office in Whitby. Whitby, North Yorkshire
Recruiter: North Yorkshire Council

Project Engineer - Forward Programmes

Grade 11 £38,629 - £41,928 per annum (Pay Award Pending)
At Derbyshire, we have been on a journey to transform the way we deliver highway services Derbyshire
Recruiter: Derbyshire County Council

Head of Highways Operations

Salary
Somerset Council
Recruiter: Somerset Council

Team Leader LGV Driver

£27,711.00 - £30,559.00, Grade 6, 37 hours, Permanent
An exciting opportunity exists in the Council’s Street Scene Services for a Team Leader LGV Driver working from our Depot at South Kirkby. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Head of Highways and Transportation

£86,196
North Tyneside Council is committed to delivering outstanding services to people and places across the borough. North Tyneside, Tyne and Wear
Recruiter: North Tyneside Metropolitan Borough Council

Works Technician

£37,399 (plus unsocial hours allowance)
The Works Technician is responsible for ensuring that the London Trams civils and off-track infrastructure Croydon (City/Town), London (Greater)
Recruiter: Transport for London

Highway Network Technician - WMF2090e

£27,711 - £28,624
We are looking to recruit a friendly and motivated candidate to join our Highways Maintenance Team as Highways Network Technician. Kendal, Cumbria
Recruiter: Westmorland and Furness Council

Strategic Sites Transport Planner

£47,754 - £51,802 (Plus £4000 Market Forces Supplement) (Pay award pending)
Worcestershire County Council and Wychavon District Council are seeking to appoint an ambitious transport planner. Pershore, Worcestershire
Recruiter: Wychavon District Council

Transportation Planning Officer

Band F, SCP 26-31 (£36,124 - £40,476 per annum)
Have you got a degree in Civil Engineering, Transportation Planning, Geography or Town Planning? Sandwell, West Midlands
Recruiter: Sandwell Metropolitan Borough Council

REL Skip Driver

£27,711.00 - £30,559.00, Grade 6, 37 hours, Permanent
An opportunity exists in the Council’s Street Scene Services for an REL Skip Driver working from our depot at Castleford. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Mechanical and Electrical Engineer

£37,035- £41,511
We have an exciting opening to join our Property Team as a Mechanical & Electrical Engineer. Harrogate, North Yorkshire
Recruiter: North Yorkshire Council

Project Chargehand (4 Posts)

Grade 9 £31,344 - £33,253 per annum (Pending Pay Award)
We are looking for Project chargehands to lead teams working on highway maintenance and construction projects. Derbyshire
Recruiter: Derbyshire County Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW