NEC could be updated after Heads of the Valleys failures

08/04/2019
Rhodri Clark

Changes could be made to the New Engineering Contract and the Welsh Government’s model contract to reflect lessons learned from a long-running dispute over a road scheme.

Costain was awarded an Early Contractor Involvement (ECI) contract for the dualling of the Gilwern to Brynmawr section of the A465 Heads of the Valleys Road, expected to cost about £220m.

However, in autumn 2017 the Welsh Government announced that the scheme was taking longer than expected, the projected cost had risen by 23% and it was in dispute with Costain over liability for the cost increase.

Last week the Welsh Government admitted there had been a further increase of £54.9m in the projected cost, which now stands at £336.2m.

Transport minister Ken Skates said: 'The project has experienced further cost increases and is now projected to be some £54.9m, including VAT, over the [earlier] revised budget.'

The news comes on top of major cost increases for the first two sections of the scheme, which have been completed. The sections came in a combined £42m over budget and many months late. There are six sections in total.

The Welsh Government also confirmed that the Costain dispute has not been resolved and the dualling work would not be completed until next year. Previously a revised opening date had been set for late 2019.

Mr Skates said last week: ‘The dispute resolution process continues and we are awaiting an interim report from the WAO [Wales Audit Office] setting out, in factual terms, findings from the work they have undertaken to date. It would not be appropriate for me to comment further on the dispute whilst it is ongoing.’

He said that ECI had been implemented on a number of major trunk road projects in Wales in recent years.

‘The ECI contract involves the appointment of an integrated design and delivery team early in the development stage of the project and that whole team then taking it through outline design development, statutory process and then onto detailed design and construction,' he added.

‘The dispute resolution process has highlighted a number of areas for improvement within Welsh Government’s model contract and also within the Institution of Civil Engineers’ New Engineering Contract (NEC) suite of documents.'

Mr Skates said: ‘A comprehensive lessons learned process has been set up to ensure they are fed into current and future procurements within [the Welsh Government’s] Transport Division but also back to NEC for future updates of the NEC suite of construction contracts.’

Asked whether it accepted Mr Skates’ statement and what changes would be made, an NEC spokesman told Highways: ‘Like the minister, NEC are currently awaiting the outcome of the WAO’s review and are unable to comment further while the dispute process is ongoing. Once we have received the findings of this report, we will be happy to engage in any lessons learned process requested.’

Mr Skates said the WAO had launched an audit of the project’s commercial position last June: ‘Welsh Government officials, Costain and our employer’s agent have provided the WAO with a comprehensive package of information to enable them to understand the project position.’

He also shed more light on the difficulties engineers have encountered in widening the alignment through the rocky Clydach Gorge.

‘The project has experienced delays and cost increases due to difficulties experienced on site. Costain has highlighted that the primary reason for this is due to a complex construction solution required to address the geological feature that they have discovered in one particular location along the scheme. The solution required will impact on the construction costs and programme.

‘While the vast majority of the scheme will be completed by December 2019, completion of the full scheme will now extend into 2020. I am obviously very disappointed by this news. However, my officials are working with Costain to deliver the project as soon as practically possible.’

History of costs

The decision to dual the A465 from Abergavenny to Hirwaun was taken in 1995 by Conservative MP John Redwood, then secretary of state for Wales. The cost of the whole programme was estimated at £268m in 2000.

This estimate more than doubled to £763m in November 2009, taking account of construction price inflation and changes in design standards.

The 2009 estimate included £256m for dualling the final single-carriageway section, from Dowlais Top to Hirwaun. In July, the Government sought expressions of interest from companies for this scheme, estimating the total value at £500m.

The WAO reported in 2011 that dualling of the first two sections, Abergavenny to Gilwern and Tredegar to Dowlais Top, finished late and cost more than expected.

The Government had intended to complete the entire dualling by 2009, but the WAO said: 'The timetable has slipped significantly and the Assembly Government is now planning on the basis that the whole programme of works will be completed by 2020.' 

Problems with the first A465 dualling scheme included a £2.2m cost increase after the site of a newly demolished petrol station was found to be contaminated. The final cost was £57m, more than double the £26m forecast. The works finished over a year late.

In the second scheme, residents and businesses in the Tafarnaubach area protested over the planned demolition of local road bridges. Two temporary bridges were installed. The scheme cost £11m more than forecast and finished four months late.

The current scheme has disrupted traffic for almost four years. Last year Stagecoach reduced bus services in the area because 'unpredictable lengthy delays' on the A465 were disrupting scheduled timetables. Bus operators can be fined if services repeatedly run more than five minutes late.

Highways jobs

Senior Traffic Engineer

East Riding of Yorkshire Council
£32,029 - £34,788 per annum
Currently seeking an enthusiastic and experienced individual to manage our Traffic Team. East Riding of Yorkshire
Recuriter: East Riding of Yorkshire Council

Technician

Derbyshire County Council
£22,628 - £24,455 per annum
Two posts have become available in the Council's Highways Development Control Section Derbyshire
Recuriter: Derbyshire County Council

Head of Network Planning

Derbyshire County Council
£52,999 - £58,310 per annum
This is a key role at Derbyshire County Council that will lead the strategic and operational planning and management of... Matlock, Derbyshire
Recuriter: Derbyshire County Council

Senior Parking Manager

Brent Council
£55,638 - £58,779 p.a. inc.
As Senior Parking Manager, you will be responsible for the effective management of the Council’s Parking Services contract, and... Wembley, London (Greater)
Recuriter: Brent Council

Group Engineer (Highway Design)

Kirklees Metropolitan Council
£39,782 to £43,757 plus £3,000 Market Rate Supplement
Are you an experienced engineer looking for an opportunity to improve the lives of the local people of... Kirklees, West Yorkshire
Recuriter: Kirklees Metropolitan Council

Group Engineer (Highways Network and Asset Management)

Kirklees Metropolitan Council
£39,782 to £43,757
Looking for a Group Engineer who already has... Kirklees, West Yorkshire
Recuriter: Kirklees Metropolitan Council

Validation Officer

London Borough of Richmond upon Thames and London Borough of Wandsworth
£21,188 - £29,796
Are you looking for working arrangements that enhance your work-life balance? London (Greater)
Recuriter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Ugobus Driver (multiple positions)

Essex County Council
Up to £18938 per annum
Please note that we have permanent, fixed term and relief contract opportunities on a part time, job share and flexible working basis. The salary is u England, Essex, Chelmsford
Recuriter: Essex County Council

Principal Transport & Infrastructure Planning Officer

Essex County Council
£52000 - £57570.0 per annum
Please note this is a two year fixed term contract with a potential for extension, subject to budget and workload. Job purpose Calling all transport P England, Essex, Chelmsford
Recuriter: Essex County Council

Food Safety Environmental Health Officer

Camden London Borough Council
£36,630 to £42,490
Seeking a highly motivated and experienced Environmental Health Officer to join our busy Food Safety team. Camden, London (Greater)
Recuriter: Camden London Borough Council

Policy Planner

London Borough of Richmond upon Thames and London Borough of Wandsworth
£25,327 - £36,486 depending on skills and experience
We have an exciting opportunity within the Spatial and Transport Planning service for 2 x Policy Planner roles... London (Greater)
Recuriter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Highways Inspector

Cambridgeshire County Council
£19,554 - £23,836
Looking for candidates who have experience of highways maintenance and have a sound technical understanding of highways. Cambridgeshire
Recuriter: Cambridgeshire County Council

Street Services Recruitment Day

Royal Borough of Greenwich
Competitive Salary
This role involves collecting residents and business wheelie bins and waste containers you will work as... Greenwich, London (Greater)
Recuriter: Royal Borough of Greenwich

Director of External Operations

Somerset West and Taunton Council
£100,000
Somerset West and Taunton Council has been through a transformation that puts customers at the heart of everything we do. Taunton, Somerset
Recuriter: Somerset West and Taunton Council

Highways on Fridays

Latest Issue

latest magazine issue
  • HIghways Awards shortlist revealed
  • Equity in transport
  • DMRB updates
View the latest issue

Latest Video