NEC could be updated after Heads of the Valleys failures

08/04/2019 | RHODRI CLARK

Changes could be made to the New Engineering Contract and the Welsh Government’s model contract to reflect lessons learned from a long-running dispute over a road scheme.

Costain was awarded an Early Contractor Involvement (ECI) contract for the dualling of the Gilwern to Brynmawr section of the A465 Heads of the Valleys Road, expected to cost about £220m.

However, in autumn 2017 the Welsh Government announced that the scheme was taking longer than expected, the projected cost had risen by 23% and it was in dispute with Costain over liability for the cost increase.

Last week the Welsh Government admitted there had been a further increase of £54.9m in the projected cost, which now stands at £336.2m.

Transport minister Ken Skates said: 'The project has experienced further cost increases and is now projected to be some £54.9m, including VAT, over the [earlier] revised budget.'

The news comes on top of major cost increases for the first two sections of the scheme, which have been completed. The sections came in a combined £42m over budget and many months late. There are six sections in total.

The Welsh Government also confirmed that the Costain dispute has not been resolved and the dualling work would not be completed until next year. Previously a revised opening date had been set for late 2019.

Mr Skates said last week: ‘The dispute resolution process continues and we are awaiting an interim report from the WAO [Wales Audit Office] setting out, in factual terms, findings from the work they have undertaken to date. It would not be appropriate for me to comment further on the dispute whilst it is ongoing.’

He said that ECI had been implemented on a number of major trunk road projects in Wales in recent years.

‘The ECI contract involves the appointment of an integrated design and delivery team early in the development stage of the project and that whole team then taking it through outline design development, statutory process and then onto detailed design and construction,' he added.

‘The dispute resolution process has highlighted a number of areas for improvement within Welsh Government’s model contract and also within the Institution of Civil Engineers’ New Engineering Contract (NEC) suite of documents.'

Mr Skates said: ‘A comprehensive lessons learned process has been set up to ensure they are fed into current and future procurements within [the Welsh Government’s] Transport Division but also back to NEC for future updates of the NEC suite of construction contracts.’

Asked whether it accepted Mr Skates’ statement and what changes would be made, an NEC spokesman told Highways: ‘Like the minister, NEC are currently awaiting the outcome of the WAO’s review and are unable to comment further while the dispute process is ongoing. Once we have received the findings of this report, we will be happy to engage in any lessons learned process requested.’

Mr Skates said the WAO had launched an audit of the project’s commercial position last June: ‘Welsh Government officials, Costain and our employer’s agent have provided the WAO with a comprehensive package of information to enable them to understand the project position.’

He also shed more light on the difficulties engineers have encountered in widening the alignment through the rocky Clydach Gorge.

‘The project has experienced delays and cost increases due to difficulties experienced on site. Costain has highlighted that the primary reason for this is due to a complex construction solution required to address the geological feature that they have discovered in one particular location along the scheme. The solution required will impact on the construction costs and programme.

‘While the vast majority of the scheme will be completed by December 2019, completion of the full scheme will now extend into 2020. I am obviously very disappointed by this news. However, my officials are working with Costain to deliver the project as soon as practically possible.’

History of costs

The decision to dual the A465 from Abergavenny to Hirwaun was taken in 1995 by Conservative MP John Redwood, then secretary of state for Wales. The cost of the whole programme was estimated at £268m in 2000.

This estimate more than doubled to £763m in November 2009, taking account of construction price inflation and changes in design standards.

The 2009 estimate included £256m for dualling the final single-carriageway section, from Dowlais Top to Hirwaun. In July, the Government sought expressions of interest from companies for this scheme, estimating the total value at £500m.

The WAO reported in 2011 that dualling of the first two sections, Abergavenny to Gilwern and Tredegar to Dowlais Top, finished late and cost more than expected.

The Government had intended to complete the entire dualling by 2009, but the WAO said: 'The timetable has slipped significantly and the Assembly Government is now planning on the basis that the whole programme of works will be completed by 2020.' 

Problems with the first A465 dualling scheme included a £2.2m cost increase after the site of a newly demolished petrol station was found to be contaminated. The final cost was £57m, more than double the £26m forecast. The works finished over a year late.

In the second scheme, residents and businesses in the Tafarnaubach area protested over the planned demolition of local road bridges. Two temporary bridges were installed. The scheme cost £11m more than forecast and finished four months late.

The current scheme has disrupted traffic for almost four years. Last year Stagecoach reduced bus services in the area because 'unpredictable lengthy delays' on the A465 were disrupting scheduled timetables. Bus operators can be fined if services repeatedly run more than five minutes late.

Highways InProfile

latest magazine issue
Highways jobs

Head of Highways Contracts & Network

£81,803 progressing to £90,664 per annum
This role is fundamental to the success of the Highways Service. Hertfordshire
Recruiter: Hertfordshire County Council

Senior Civil Engineer - Major Projects x 4

£45,894.00 - £54,952.00
We are looking for experienced engineers to help us progress a number of key projects and programmes Glasgow, Glasgow City
Recruiter: Transport Scotland

Technician - Maintenance

£31001.0000 - £36471.0000 per annum
Essex Highways is responsible for managing and maintaining one of the largest highway networks in the country
Recruiter: Essex County Council

Highways Contract Engineer

£46,731 - £49,764
The team helps provide a safe road network that operates efficiently and effectively.  Northamptonshire
Recruiter: North Northamptonshire Council

Principal Transport Planner

£46,731 - £49,764 (pro-rata)
We are looking for an experienced professional to join us on a six-month temporary contact as a Principal Transport Planner. Kettering, Northamptonshire
Recruiter: North Northamptonshire Council

Highways Maintenance Operative

£Competitive
We have a fantastic opportunity for a Permanent Highways Maintenance Operative Broughton, Brigg
Recruiter: Amey

Head of Highways Contracts & Network

£81,803 progressing to £90,664 per annum
The team includes approximately 60 directly employed HCC people Hertfordshire
Recruiter: Hertfordshire County Council

Principal Construction Manager

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Principal Construction Manager Yorkshire and the Humber
Recruiter: Amey

Quality Technician

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Quality Technician Yorkshire and the Humber
Recruiter: Amey

Senior Highway Engineer (Development Management)

£42679.0000 - £50211.0000 per annum
Senior Highway Engineer (Development Management)Permanent, Full Time£43,960 to £51,718 per annum*Location
Recruiter: Essex County Council

Project Manager (Major Projects)

£44,711 - £47,754
Are you an experienced project professional or engineer with looking to take the next step in your career? Halifax, West Yorkshire
Recruiter: Calderdale Metropolitan Borough Council

Senior Civil Engineer - Roads

£45,894 - £54,952
Are you an experienced engineer looking to support the Scottish Government’s national objectives. Scotland
Recruiter: Transport Scotland

Project Team Manager

£55,147 to £60,676 per annum
We are pleased to be able to offer an opportunity for a role as Design Team Manager Norwich, Norfolk
Recruiter: Norfolk County Council

Clerk of Works

GRADE 08 (£37,938 - £41,511)
Warrington is one of the most successful towns in the country Warrington, Cheshire
Recruiter: Warrington Borough Council

Assistant Projects Engineer

GRADE 06 (£29,093 - £32,654),GRADE 07 (£33,366 - £37,035), GRADE 08 (£37,938 - £41,511)
Warrington is one of the most successful towns in the country Warrington, Cheshire
Recruiter: Warrington Borough Council

Principal Engineer - Traffic Management

£45,718 - £48,710 per annum
At Bath & North East Somerset Council we have one overriding purpose – to improve people’s lives. Bath, Somerset
Recruiter: Bath & North East Somerset Council

Vehicle Technician - Improver

£28,624 - £30,060
Transport Services is responsible for all aspects of transport and related services Huddersfield, West Yorkshire
Recruiter: Kirklees Metropolitan Council

Programme Delivery Office Administrator

Grade 9 £31,344 - £33,253 per annum
At Derbyshire, we have been on a journey to transform the way we deliver highway services to make them fit for the future Derbyshire
Recruiter: Derbyshire County Council

Support Officer - Highways Asset Management Systems

£31,586 - £34,314
We are a forward-thinking organisation dedicated to maintaining and improving our highway infrastructure. Lincolnshire
Recruiter: Lincolnshire County Council

Principal Transport Planner (Strategy)

£46,731-£49,764
We are looking for an experienced professional to join North Northamptonshire Council as a Principal Transport Planner (Strategy). Sheerness House, 41 Meadow Road, Kettering moving to Haylock House, Kettering Parkway, Kettering NN15 6EY, United Kingdom
Recruiter: North Northamptonshire Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW