NEC could be updated after Heads of the Valleys failures

08/04/2019 | RHODRI CLARK

Changes could be made to the New Engineering Contract and the Welsh Government’s model contract to reflect lessons learned from a long-running dispute over a road scheme.

Costain was awarded an Early Contractor Involvement (ECI) contract for the dualling of the Gilwern to Brynmawr section of the A465 Heads of the Valleys Road, expected to cost about £220m.

However, in autumn 2017 the Welsh Government announced that the scheme was taking longer than expected, the projected cost had risen by 23% and it was in dispute with Costain over liability for the cost increase.

Last week the Welsh Government admitted there had been a further increase of £54.9m in the projected cost, which now stands at £336.2m.

Transport minister Ken Skates said: 'The project has experienced further cost increases and is now projected to be some £54.9m, including VAT, over the [earlier] revised budget.'

The news comes on top of major cost increases for the first two sections of the scheme, which have been completed. The sections came in a combined £42m over budget and many months late. There are six sections in total.

The Welsh Government also confirmed that the Costain dispute has not been resolved and the dualling work would not be completed until next year. Previously a revised opening date had been set for late 2019.

Mr Skates said last week: ‘The dispute resolution process continues and we are awaiting an interim report from the WAO [Wales Audit Office] setting out, in factual terms, findings from the work they have undertaken to date. It would not be appropriate for me to comment further on the dispute whilst it is ongoing.’

He said that ECI had been implemented on a number of major trunk road projects in Wales in recent years.

‘The ECI contract involves the appointment of an integrated design and delivery team early in the development stage of the project and that whole team then taking it through outline design development, statutory process and then onto detailed design and construction,' he added.

‘The dispute resolution process has highlighted a number of areas for improvement within Welsh Government’s model contract and also within the Institution of Civil Engineers’ New Engineering Contract (NEC) suite of documents.'

Mr Skates said: ‘A comprehensive lessons learned process has been set up to ensure they are fed into current and future procurements within [the Welsh Government’s] Transport Division but also back to NEC for future updates of the NEC suite of construction contracts.’

Asked whether it accepted Mr Skates’ statement and what changes would be made, an NEC spokesman told Highways: ‘Like the minister, NEC are currently awaiting the outcome of the WAO’s review and are unable to comment further while the dispute process is ongoing. Once we have received the findings of this report, we will be happy to engage in any lessons learned process requested.’

Mr Skates said the WAO had launched an audit of the project’s commercial position last June: ‘Welsh Government officials, Costain and our employer’s agent have provided the WAO with a comprehensive package of information to enable them to understand the project position.’

He also shed more light on the difficulties engineers have encountered in widening the alignment through the rocky Clydach Gorge.

‘The project has experienced delays and cost increases due to difficulties experienced on site. Costain has highlighted that the primary reason for this is due to a complex construction solution required to address the geological feature that they have discovered in one particular location along the scheme. The solution required will impact on the construction costs and programme.

‘While the vast majority of the scheme will be completed by December 2019, completion of the full scheme will now extend into 2020. I am obviously very disappointed by this news. However, my officials are working with Costain to deliver the project as soon as practically possible.’

History of costs

The decision to dual the A465 from Abergavenny to Hirwaun was taken in 1995 by Conservative MP John Redwood, then secretary of state for Wales. The cost of the whole programme was estimated at £268m in 2000.

This estimate more than doubled to £763m in November 2009, taking account of construction price inflation and changes in design standards.

The 2009 estimate included £256m for dualling the final single-carriageway section, from Dowlais Top to Hirwaun. In July, the Government sought expressions of interest from companies for this scheme, estimating the total value at £500m.

The WAO reported in 2011 that dualling of the first two sections, Abergavenny to Gilwern and Tredegar to Dowlais Top, finished late and cost more than expected.

The Government had intended to complete the entire dualling by 2009, but the WAO said: 'The timetable has slipped significantly and the Assembly Government is now planning on the basis that the whole programme of works will be completed by 2020.' 

Problems with the first A465 dualling scheme included a £2.2m cost increase after the site of a newly demolished petrol station was found to be contaminated. The final cost was £57m, more than double the £26m forecast. The works finished over a year late.

In the second scheme, residents and businesses in the Tafarnaubach area protested over the planned demolition of local road bridges. Two temporary bridges were installed. The scheme cost £11m more than forecast and finished four months late.

The current scheme has disrupted traffic for almost four years. Last year Stagecoach reduced bus services in the area because 'unpredictable lengthy delays' on the A465 were disrupting scheduled timetables. Bus operators can be fined if services repeatedly run more than five minutes late.

Highways InProfile

latest magazine issue
Highways jobs

Mobile Street Scene Operative

£24,796 - £25,989 per annum
We are currently looking for a Mobile Cleansing Operative to join our Northallerton team. Northallerton, North Yorkshire
Recruiter: North Yorkshire Council

Highway Design and Construction Manager

Grade N, scp50 £62,443 to scp53 £65,663 per annum, plus essential car user allowance
We embrace AI to enhance our operations and to innovate our services. Bolton, Greater Manchester
Recruiter: Bolton Council

Asset Senior Maintenance Engineer (CDC)

Grade 10, £47,154 – £51,235
Do you have a positive approach to work and enjoy the challenge of a busy role? Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Structures Engineer

£40,777-£45,091
We are seeking to recruit a Highway Structures Engineer - Asset Management Graded 11. The post holder will be responsible for undertaking the workloa Durham
Recruiter: Durham County Council

Arboricultural Consultant

£36168.0000 - £42551.0000 per annum
Arboricultural ConsultantPermanentFull Time, 37 hours per week£36,168 to £42,551 per annumLocation
Recruiter: Essex County Council

Flood Risk Engineer - Epping Forest District Council

£40.0000 - £45.0000 per hour
Flood Risk Engineer Epping, EssexFull-Time, Temporary 37 Hours per Week 3 Months Contract* £40-£45 per hour, Umbrella Closing Date
Recruiter: Essex County Council

Senior Engineer

Starting Salary from £43,545 based on skills and
Job TitleSenior Engineer (x2 v... Frogmore Complex, Wandsworth, London,
Recruiter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Electrical Design Engineer

Grade 9 £35,412 to £39,152 - Grade 10 £38,220 to £41,771 - Grade 11 £40,777 to £45,091 - Grade 12 £44,075 to £48,226 p.a.
The Construction Consultancy Services (CCS) team provide client-side construction consultancy services across a range of professional disciplines to d Durham
Recruiter: Durham County Council

Street Lighting Electrician CDC

Grade 8, £33,708 - £37,399
Highways Operations is a growing service area within the Place directorate. Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Assistant Traffic Management Technician - WMF2311e

£26,403 - £26,824
This is a predominantly office-based role with some site visits required. Penrith, Cumbria
Recruiter: Westmorland and Furness Council

Senior Lawyer Planning and Highways - WMF2312e

£56,883 - £59,198
To be a success in our Legal Team you will have experience as a Planning and Highways Lawyer Cumbria / Various
Recruiter: Westmorland and Furness Council

Street Cleansing Operative

£26,403.00 - £28,142.00, Grade 5, 37 hours, Permanent
An opportunity exists in the Council's Street Scene Services for a Street Cleansing Operative Wakefield, West Yorkshire
Recruiter: Wakefield Council

Civil Engineering Technician (HDM)

Grade 4 - Grade 6
Do you want to join a team helping to shape the future of Wakefield through Highways Development Management? Wakefield, West Yorkshire
Recruiter: Wakefield Council

Highways Maintenance Operative Apprentice

£28,729.00 per annum (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management operative course Staffordshire
Recruiter: Amey

Highways Maintenance Operative Apprentice

£28,729.00 per annum (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management Operative level 2 apprenticeship Goole, East Riding of Yorkshire
Recruiter: Amey

Highways Maintenance Operative Apprentice

£28,729 (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management Operative level 2 apprenticeship Rothersthorpe, Northampton
Recruiter: Amey

Head of Design Services

£77,536 - £83,366
You will lead the delivery of a high-performing Technical Services Partnership (TSP). Lincolnshire
Recruiter: Lincolnshire County Council

Highways Maintenance Operative Apprentice

£28,729.00 per annum (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management Operative level 2 apprenticeship Ecclesfield, Sheffield
Recruiter: Amey

Highways Maintenance Operative Apprentice

£28,729.00 per annum (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management Operative level 2 apprenticeship. Barnsley, South Yorkshire
Recruiter: Amey

Highways Maintenance Operative Apprentice

£28,729.00 per annum (Subject to review)
As part of your apprenticeship, you will be enrolled onto a Lead Traffic Management Operative level 2 apprenticeship Knottingley, West Yorkshire
Recruiter: Amey
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW