Costain and Welsh Government agree A465 settlement24/02/2021 Costain has agreed a settlement with the Welsh Government over changes to its contract for a major widening of the A465 but declined to confirm the exact value. |
Heads of the Valleys dualling scheme to cost over £100m a mile17/11/2020 The Welsh Government has denied understating the construction cost of the final A465 dualling scheme as details of the future cost to taxpayers over three decades have belatedly emerged. |
Consortium named for £500m final A465 sections23/06/2020 The Welsh Government has confirmed its preferred bidder for the final two sections of the troubled A465 Heads of the Valleys dualling scheme. |
Welsh Government sets aside £2m for A465 legal costs24/02/2020 The Welsh Government has budgeted £2m for legal fees in its wrangle with Costain over the A465 dualling between Gilwern and Brynmawr, the Wales Audit Office has revealed. |
NEC could be updated after Heads of the Valleys failures08/04/2019 Changes could be made to the New Engineering Contract and the Welsh Government’s model contract to reflect lessons learned from a long-running dispute over a road scheme. |
Plans on display for Heads of the Valleys dualling project25/11/2015 Proposed plans for the final section of the £800m A465 Heads of the Valleys dualling project in Wales will go on display next month (December). |
Call to scrap All Lane Running as smart motorway deaths rise
Panorama: Faulty smart motorway tech 'means Russian roulette'
Exclusive: A quarter of smart motorway schemes fall below safety benchmark