In search of lost time: M25 delay estimates don't add up

22/03/2024 | CHRIS AMES

National Highways' formal appraisal of its flagship M25 Junction 10 scheme significantly understated the impact and cost of delays during construction, a Highways investigation suggests.

As Highways has reported, the £317m scheme, which began last year and is due to run to the summer of 2025, has caused major jams, with nearly two million vehicle hours of delay last year. This figure is based on delays to vehicles remaining on the mainline.

Using values in official WebTAG guidance and National Highways’ data, Highways has calculated the likely cost of the delays to all vehicles to be around £30m a year. 

However, the economic evaluation for the scheme’s planning application used an estimate of £11m for the total cost of delays caused by the scheme's construction. This was half the amount provided in an earlier estimate of £23m and just a quarter of a £45m forecast produced the same year.

The figure of £23m (at 2010 prices) appears in a National Highways (known then as Highways England) November 2017 Scheme Assessment Report and was based mainly on reducing speed limits to 50mph on the M25 and A3 mainline in the immediate vicinity of the junction.

This was despite the report assessing that construction 'would involve a complex programme of traffic management on the live highways, including: reduced speed limits, narrow lanes, lane closures, overnight closures of the road with diversions'.

 

In 2017 National Highways decided to take forward Option 14

However, the scheme’s April 2020 Combined Modelling and Appraisal Report, obtained under freedom of information laws, calculated a cost to the economy of just £11m, based on the same assumptions and methodology.

The appraisal report gave the scheme a benefit cost ratio (BCR) of 2.22. The Planning Inspectorate (PINS) recommendation report, sent to the DfT in October 2020, cites this BCR.

However, the scheme’s traffic management plan (TMP) predicted that there would be lengthy delays for vehicles using the junction to change from the M25 to the A3 or vice versa and estimated the cost at £15m a year for each of three years, therefore totalling £45m.

Asked to explain why the appraisal report had the lower figure, a National Highways spokesperson told Highways that the Combined Modelling and Appraisal Report was 'based on the best knowledge at the time, in this case 2020'.

It added that the TMP is 'a detailed plan once the construction methods are fully known and takes into account the method, safety and our customers into its assumptions. The value presented in the Traffic Management Plan is based on more up to date information’.

However, the TMP states: ‘Construction period is January 2021 to December 2023’ - meaning it must have been written no later than 2020. 

The first iteration of the TMP is dated just four days after the PINS report in October 2020, which suggests that the estimates within it were generated while PINS was considering the case - raising questions about why the £45m figure was not made available.

The TMP was produced well ahead of the decision in May 2022, by the then transport secretary, Grant Shapps, to grant the scheme’s Development Consent Order (DCO), based on PINS’ recommendation.

The final iteration of the TMP was published the same month. It was a requirement of the DCO and the published version is stated to have been produced ‘for discharge of requirement’.

Highways asked the DfT whether it was aware when the DCO was granted that National Highways was predicting a much greater economic impact of the delays than it used in its application. It refused to answer.

It is also clear that National Highways was aware at the time of the appraisal report that lane closures on slip roads would impact traffic flow and the TMP assumed that lanes on the mainline would largely remain open.

The loss of lanes on slip roads and the junction roundabout has subsequently proved to be the major cause of delays, causing huge tailbacks onto the main carriageway. This suggests that a valid estimate of the impact of the scheme would have covered both types of journey.

National Highways told Highways that the increase in delays for vehicles remaining on the carriageway last summer ‘reflects the introduction of traffic management on the sensitive slip roads leading on/off J10’.

Becca Lush of campaign group Transport Action Network (TAN), who obtained the appraisal report, told Highways: ‘TAN is not surprised that National Highways is underestimating the costs of its major road projects, including the construction delays.

‘Downplaying costs and exaggerating benefits seems to be endemic in road appraisal. It hoodwinks ministers into approving expensive and damaging projects which don't deliver value for money. It's time there was a light shone on this rather murky process, even more so when money is tight.’

Highways also asked National Highways whether it expected the extent of the disruption and whether it has conducted any kind of lessons learned exercise.

The company said that it anticipated a ‘notable’ impact on daily traffic flow and that it had sought to ‘minimise’ disruption.

Highways InProfile

latest magazine issue
Highways jobs

Customer Support Officer

Up to £33291 per annum
Support businesses, serve communities and help deliver a service that keeps our borough clean and efficient.Support businesses, serve communities and England, London, City of London
Recruiter: The Royal Borough of Kensington & Chelsea Council

Estate Manager

Up to £39150 per annum
Lead from the front. Keep our estates clean, safe and welcoming - and help build stronger communities every day.Lead from the front. Keep our estates England, London, City of London
Recruiter: The Royal Borough of Kensington & Chelsea Council

Civil Enforcement Officer

£25,989 - £27,254 per annum
We’re looking for Civil Enforcement officers to join our parking services team. Selby, North Yorkshire
Recruiter: North Yorkshire Council

Waste and Recycling Manager

£64,355.20 - £70,397.60 per year
As Waste and Recycling Manager your role will be to oversee and manage the Waste Management Services Contract Aberdeen, Aberdeenshire
Recruiter: Aberdeen City Council

Director of Streets and Environment

£129,901 - £135,064
This is an exciting time to be joining Croydon. Croydon (City/Town), London (Greater)
Recruiter: Croydon Council

Highway Maintenance & Drainage Manager

£59,568 - £66,801
As our Highway Maintenance & Drainage Manager Civic Centre, Keynsham
Recruiter: Bath & North East Somerset Council

Director of Transport

£100,088 – £110,736
The York and North Yorkshire Combined Authority was established as a new organisation in early 2024. Northallerton, North Yorkshire
Recruiter: York and North Yorkshire Combined Authority

Head of Economic Development

Grade 14 £54,867 - £60,971 per annum
Are you passionate about making a positive impact on the environment and shaping a sustainable future? Derbyshire
Recruiter: Derbyshire County Council

Major Projects Manager

Grade £54,867 - £60,971 per annum
Do you want to make a real difference to ‘place’, be the driving force behind major capital projects and directly impact people’s lives? Derbyshire
Recruiter: Derbyshire County Council

Director of Transport

£112,924
East Midlands Combined County Authority (EMCCA) is on a bold journey. East Midlands Region
Recruiter: East Midlands Combined County Authority

Highways Network Engineer - WMF2169e

£45,091 - £46,142
This position offers a unique opportunity to make a lasting impact on the resilience and effectiveness of our highway network. Kendal,Penrith or Barrow
Recruiter: Westmorland and Furness Council

Highway Network Technician - WMF2168e

£28,598 - £29,540
This role offers an excellent opportunity to gain experience in a specialised area of highways operations while contributing directly Kendal, Penrith or Barrow
Recruiter: Westmorland and Furness Council

Director of Streetscene

£94,972 - £108,767
We continue to have big ambitions for our borough Fareham, Hampshire
Recruiter: Fareham Borough Council

Principal Engineer - Urban Traffic Control (UTC)

£44,711 - £49,764
Liverpool is home to vibrant, energetic and engaged communities. Liverpool, Merseyside
Recruiter: Liverpool City Council

Lawyer 2- Planning and Highways

£49,764 - £54,181
We are looking for a fresh thinking and enthusiastic Planning and Highways Lawyer Hereford, Herefordshire
Recruiter: Herefordshire Council

Development Engineer

£35,967 - £41,268 per annum
Are you ready to play a key role in shaping and safeguarding the future of our highways and public spaces? Bexley (City/Town), London (Greater)
Recruiter: London Borough of Bexley

Highways Assistant Engineer WMF2133e

£39,513 to £40,476
We have an exciting opportunity for the right person to work within the challenging and ever-changing landscape. Penrith, Cumbria
Recruiter: Westmorland and Furness Council

PRINCIPAL TRANSPORT PLANNING OFFICER

£43693 - £46731
We have an exciting opportunity for an experienced professional to join our team in Hull as a Principal Transport Planning Officer. Kingston upon Hull, East Riding of Yorkshire
Recruiter: Hull City Council

HIGHWAYS AND TRAFFIC ENGINEER - 4 POSTS

£43693 - £46731
We have several exciting opportunities for suitably qualified Highways Civil Engineers and Traffic Engineers Wilson Centre, 1st floor, Hull HU1 2AG
Recruiter: Hull City Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW