In search of lost time: M25 delay estimates don't add up

22/03/2024
Chris Ames

National Highways' formal appraisal of its flagship M25 Junction 10 scheme significantly understated the impact and cost of delays during construction, a Highways investigation suggests.

As Highways has reported, the £317m scheme, which began last year and is due to run to the summer of 2025, has caused major jams, with nearly two million vehicle hours of delay last year. This figure is based on delays to vehicles remaining on the mainline.

Using values in official WebTAG guidance and National Highways’ data, Highways has calculated the likely cost of the delays to all vehicles to be around £30m a year. 

However, the economic evaluation for the scheme’s planning application used an estimate of £11m for the total cost of delays caused by the scheme's construction. This was half the amount provided in an earlier estimate of £23m and just a quarter of a £45m forecast produced the same year.

The figure of £23m (at 2010 prices) appears in a National Highways (known then as Highways England) November 2017 Scheme Assessment Report and was based mainly on reducing speed limits to 50mph on the M25 and A3 mainline in the immediate vicinity of the junction.

This was despite the report assessing that construction 'would involve a complex programme of traffic management on the live highways, including: reduced speed limits, narrow lanes, lane closures, overnight closures of the road with diversions'.

 

In 2017 National Highways decided to take forward Option 14

However, the scheme’s April 2020 Combined Modelling and Appraisal Report, obtained under freedom of information laws, calculated a cost to the economy of just £11m, based on the same assumptions and methodology.

The appraisal report gave the scheme a benefit cost ratio (BCR) of 2.22. The Planning Inspectorate (PINS) recommendation report, sent to the DfT in October 2020, cites this BCR.

However, the scheme’s traffic management plan (TMP) predicted that there would be lengthy delays for vehicles using the junction to change from the M25 to the A3 or vice versa and estimated the cost at £15m a year for each of three years, therefore totalling £45m.

Asked to explain why the appraisal report had the lower figure, a National Highways spokesperson told Highways that the Combined Modelling and Appraisal Report was 'based on the best knowledge at the time, in this case 2020'.

It added that the TMP is 'a detailed plan once the construction methods are fully known and takes into account the method, safety and our customers into its assumptions. The value presented in the Traffic Management Plan is based on more up to date information’.

However, the TMP states: ‘Construction period is January 2021 to December 2023’ - meaning it must have been written no later than 2020. 

The first iteration of the TMP is dated just four days after the PINS report in October 2020, which suggests that the estimates within it were generated while PINS was considering the case - raising questions about why the £45m figure was not made available.

The TMP was produced well ahead of the decision in May 2022, by the then transport secretary, Grant Shapps, to grant the scheme’s Development Consent Order (DCO), based on PINS’ recommendation.

The final iteration of the TMP was published the same month. It was a requirement of the DCO and the published version is stated to have been produced ‘for discharge of requirement’.

Highways asked the DfT whether it was aware when the DCO was granted that National Highways was predicting a much greater economic impact of the delays than it used in its application. It refused to answer.

It is also clear that National Highways was aware at the time of the appraisal report that lane closures on slip roads would impact traffic flow and the TMP assumed that lanes on the mainline would largely remain open.

The loss of lanes on slip roads and the junction roundabout has subsequently proved to be the major cause of delays, causing huge tailbacks onto the main carriageway. This suggests that a valid estimate of the impact of the scheme would have covered both types of journey.

National Highways told Highways that the increase in delays for vehicles remaining on the carriageway last summer ‘reflects the introduction of traffic management on the sensitive slip roads leading on/off J10’.

Becca Lush of campaign group Transport Action Network (TAN), who obtained the appraisal report, told Highways: ‘TAN is not surprised that National Highways is underestimating the costs of its major road projects, including the construction delays.

‘Downplaying costs and exaggerating benefits seems to be endemic in road appraisal. It hoodwinks ministers into approving expensive and damaging projects which don't deliver value for money. It's time there was a light shone on this rather murky process, even more so when money is tight.’

Highways also asked National Highways whether it expected the extent of the disruption and whether it has conducted any kind of lessons learned exercise.

The company said that it anticipated a ‘notable’ impact on daily traffic flow and that it had sought to ‘minimise’ disruption.

Latest Issue

latest magazine issue

ALSO INSIDE:

  • Exclusive: M25 delays data doesn't add up
  • Autonomous vehicles: Life after the hype
View the latest issue


Highways jobs

Engineer

£40,221 - £51,515
As part of a friendly and enthusiastic team, you will play an important role in designing innovative urban transport and public realm projects 100 Temple Street Redcliff Bristol BS1 6AN
Recruiter: Bristol City Council

Light Vehicle Mechanic

£27,507 - £29,418
We are looking for a highly motivated Light Vehicle Mechanic to join our County Transport team County Transport – Ambergate Workshops
Recruiter: Derbyshire County Council

Head of Transport Strategy & Road Safety

£76,594 - £84,443 per annum
We have a unique opportunity for you to shape, influence and create a better future for Warwickshire Warwickshire
Recruiter: Warwickshire County Council

Development Engineer

£34,476 - £39,777 per annum
The team requires someone who can inspect, measure and monitor highway works Bexley (London Borough), London (Greater)
Recruiter: London Borough of Bexley

Highway Asset and Development Manager

Grade N Scp 50 £59,031 to Scp 53 £62,076, plus car allowance
To be responsible for leading, developing and delivering an effective, efficient and safe Highway Asset Management Service Bolton, Greater Manchester
Recruiter: Bolton Council

Bridge Engineer

£34,834 to £39,186
We welcome applications from a diverse range of backgrounds and experiences to enrich our team. Taunton
Recruiter: Somerset Council

Highways Operatives (Lillyhall) x5

£26,421 - £27,334
Cumberland Council is a dynamic and forward-thinking authority dedicated to enhancing public services Cumbria
Recruiter: Cumberland Council

Assistant Parking Services Officer – CMB1029e

£24,294 - £24,702
Are you looking for a role where you can work independently and with a great team of people? Carlisle, Cumbria
Recruiter: Cumberland Council

Heavy Vehicle Service and Maintenance Technician Apprentice

£236.80 per week
An exciting opportunity has arisen to train as a Heavy Vehicle Service and Maintenance Technician Chelmsford, Essex
Recruiter: Chelmsford City Council

Trainee Traffic Installation Technician

Competitive + Commercial Vehicle
If successful in this role you will learn to install traffic signals, including the installation of ancillary and associated equipment and highways systems. England, Cumbria, Carlisle
Recruiter: Telent

Transport Development Officer OCC615931

£35,745 - £38,223 per annum
You will support senior colleagues in providing the highways and transport input to strategic development proposals. Oxfordshire
Recruiter: Oxfordshire County Council

Technical Lead - Oxford Workplace Parking Levy OCC616196

£47,420 - £50,512 per annum
An exciting opportunity has arisen at Oxfordshire County Council to join the Central Team Oxfordshire
Recruiter: Oxfordshire County Council

Traffic Management Order

between ME12 £42,840 and ME15 £54,129 per annum
We are looking for a self-motivated individual with an eye for detail responsible for drafting and making traffic management orders Merton, London (Greater)
Recruiter: London Borough of Merton

Team Leader LGV Driver

£26,421.00 - £29,269.00, Grade 6, 37 hours, Permanent
An exciting opportunity exists in the Council’s Street Scene Services for a Team Leader LGV Driver Wakefield, West Yorkshire
Recruiter: Wakefield Council

Waste Recycling Operative

£24,294.00 - £25,979.00, Grade 5, 37 hours, Permanent
An opportunity exists in the Council’s Street Scene Services for a Waste Recycling Operative. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Recycling Centre Site Operatives

Up to £23344 per annum + Per Annum, Pro Rata if part time
Recycling Centre Site OperativesPermanent, Full Time£23,344 per annum (pro-rata for part time roles)Location
Recruiter: Essex County Council

Streetworks Compliance Officer

£33,945 - £34,834
This is an exciting opportunity to join a new Streetworks Team Cumbria
Recruiter: Westmorland and Furness Council

Administration Assistant

£24,294 – 25,979 pro rata
We have an opportunity for an enthusiastic and capable person. Accrington, Lancashire
Recruiter: Hyndburn Borough Council

Mechanic (LCV/LGV)

£32,076 - £33,945 Plus Tool Allowance
The successful applicant will inspect, service and repair a variety of vehicles (LCV/LGV) Accrington, Lancashire
Recruiter: Hyndburn Borough Council

Contract Officer BDR

Band H - Band J £33,024 - £43,421 (pay award pending)
We are looking for an enthusiastic, talented, motivated, and ambitious person to become the BDR Contract Officer. Rotherham, South Yorkshire
Recruiter: Rotherham Metropolitan Borough Council

Highways Presents

 


Latest Video