In search of lost time: M25 delay estimates don't add up

22/03/2024 | CHRIS AMES

National Highways' formal appraisal of its flagship M25 Junction 10 scheme significantly understated the impact and cost of delays during construction, a Highways investigation suggests.

As Highways has reported, the £317m scheme, which began last year and is due to run to the summer of 2025, has caused major jams, with nearly two million vehicle hours of delay last year. This figure is based on delays to vehicles remaining on the mainline.

Using values in official WebTAG guidance and National Highways’ data, Highways has calculated the likely cost of the delays to all vehicles to be around £30m a year. 

However, the economic evaluation for the scheme’s planning application used an estimate of £11m for the total cost of delays caused by the scheme's construction. This was half the amount provided in an earlier estimate of £23m and just a quarter of a £45m forecast produced the same year.

The figure of £23m (at 2010 prices) appears in a National Highways (known then as Highways England) November 2017 Scheme Assessment Report and was based mainly on reducing speed limits to 50mph on the M25 and A3 mainline in the immediate vicinity of the junction.

This was despite the report assessing that construction 'would involve a complex programme of traffic management on the live highways, including: reduced speed limits, narrow lanes, lane closures, overnight closures of the road with diversions'.

 

In 2017 National Highways decided to take forward Option 14

However, the scheme’s April 2020 Combined Modelling and Appraisal Report, obtained under freedom of information laws, calculated a cost to the economy of just £11m, based on the same assumptions and methodology.

The appraisal report gave the scheme a benefit cost ratio (BCR) of 2.22. The Planning Inspectorate (PINS) recommendation report, sent to the DfT in October 2020, cites this BCR.

However, the scheme’s traffic management plan (TMP) predicted that there would be lengthy delays for vehicles using the junction to change from the M25 to the A3 or vice versa and estimated the cost at £15m a year for each of three years, therefore totalling £45m.

Asked to explain why the appraisal report had the lower figure, a National Highways spokesperson told Highways that the Combined Modelling and Appraisal Report was 'based on the best knowledge at the time, in this case 2020'.

It added that the TMP is 'a detailed plan once the construction methods are fully known and takes into account the method, safety and our customers into its assumptions. The value presented in the Traffic Management Plan is based on more up to date information’.

However, the TMP states: ‘Construction period is January 2021 to December 2023’ - meaning it must have been written no later than 2020. 

The first iteration of the TMP is dated just four days after the PINS report in October 2020, which suggests that the estimates within it were generated while PINS was considering the case - raising questions about why the £45m figure was not made available.

The TMP was produced well ahead of the decision in May 2022, by the then transport secretary, Grant Shapps, to grant the scheme’s Development Consent Order (DCO), based on PINS’ recommendation.

The final iteration of the TMP was published the same month. It was a requirement of the DCO and the published version is stated to have been produced ‘for discharge of requirement’.

Highways asked the DfT whether it was aware when the DCO was granted that National Highways was predicting a much greater economic impact of the delays than it used in its application. It refused to answer.

It is also clear that National Highways was aware at the time of the appraisal report that lane closures on slip roads would impact traffic flow and the TMP assumed that lanes on the mainline would largely remain open.

The loss of lanes on slip roads and the junction roundabout has subsequently proved to be the major cause of delays, causing huge tailbacks onto the main carriageway. This suggests that a valid estimate of the impact of the scheme would have covered both types of journey.

National Highways told Highways that the increase in delays for vehicles remaining on the carriageway last summer ‘reflects the introduction of traffic management on the sensitive slip roads leading on/off J10’.

Becca Lush of campaign group Transport Action Network (TAN), who obtained the appraisal report, told Highways: ‘TAN is not surprised that National Highways is underestimating the costs of its major road projects, including the construction delays.

‘Downplaying costs and exaggerating benefits seems to be endemic in road appraisal. It hoodwinks ministers into approving expensive and damaging projects which don't deliver value for money. It's time there was a light shone on this rather murky process, even more so when money is tight.’

Highways also asked National Highways whether it expected the extent of the disruption and whether it has conducted any kind of lessons learned exercise.

The company said that it anticipated a ‘notable’ impact on daily traffic flow and that it had sought to ‘minimise’ disruption.

Highways InProfile

latest magazine issue
Highways jobs

Highways Maintenance Manager

£49,764 - £53,817 per annum
We are looking for an experienced co-ordinator to join the team as a Highways Maintenance Manager Skipton, North Yorkshire
Recruiter: North Yorkshire Council

Civil Enforcement Officer

£25,183 - £26,409
Are you looking for a role that allows you to earn whilst been outdoors across the district of North Yorkshire? Whitby, North Yorkshire
Recruiter: North Yorkshire Council

Civil Enforcement Officer

£25,183 - £26,409
Are you looking for a role that allows you to earn whilst been outdoors across the district of North Yorkshire? Northallerton, North Yorkshire
Recruiter: North Yorkshire Council

Senior Street Cleansing Technician (CDC)

Grade 6, £25,175 - £25,983 (Pay award pending) + 6% AIA
We are about to embark on an ambitious programme of change in our city centre Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Highways Improvement Manager

£49,764 - £53,817 per annum
Would you like to be part of our friendly, supportive, Highways team? Scarborough, North Yorkshire
Recruiter: North Yorkshire Council

Highways Delivery Manager

£69,123 - £72,783
This is an exciting role leading maintenance and construction delivery. Northumberland
Recruiter: Northumberland County Council

UGO Bus Driver

Up to £25081.00 per annum
UGO Bus DriverPermanent, Part TimeUp to £25,081 per annum (full time equivalent)Location
Recruiter: Essex County Council

Street Scene Workforce Support Officer

£27,711.00 - £30,559.00, Grade 6, 37 hours, Permanent
An opportunity exists in the Council’s Street Scene Services for a Street Scene Workforce Support Officer Wakefield, West Yorkshire
Recruiter: Wakefield Council

Highways Officer

£33,366 - £37,035 per annum
We are seeking to recruit a Highways Officer based at our Highways Office in Whitby. Whitby, North Yorkshire
Recruiter: North Yorkshire Council

Project Engineer - Forward Programmes

Grade 11 £38,629 - £41,928 per annum (Pay Award Pending)
At Derbyshire, we have been on a journey to transform the way we deliver highway services Derbyshire
Recruiter: Derbyshire County Council

Head of Highways Operations

Salary
Somerset Council
Recruiter: Somerset Council

Team Leader LGV Driver

£27,711.00 - £30,559.00, Grade 6, 37 hours, Permanent
An exciting opportunity exists in the Council’s Street Scene Services for a Team Leader LGV Driver working from our Depot at South Kirkby. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Head of Highways and Transportation

£86,196
North Tyneside Council is committed to delivering outstanding services to people and places across the borough. North Tyneside, Tyne and Wear
Recruiter: North Tyneside Metropolitan Borough Council

Works Technician

£37,399 (plus unsocial hours allowance)
The Works Technician is responsible for ensuring that the London Trams civils and off-track infrastructure Croydon (City/Town), London (Greater)
Recruiter: Transport for London

Highway Network Technician - WMF2090e

£27,711 - £28,624
We are looking to recruit a friendly and motivated candidate to join our Highways Maintenance Team as Highways Network Technician. Kendal, Cumbria
Recruiter: Westmorland and Furness Council

Strategic Sites Transport Planner

£47,754 - £51,802 (Plus £4000 Market Forces Supplement) (Pay award pending)
Worcestershire County Council and Wychavon District Council are seeking to appoint an ambitious transport planner. Pershore, Worcestershire
Recruiter: Wychavon District Council

Transportation Planning Officer

Band F, SCP 26-31 (£36,124 - £40,476 per annum)
Have you got a degree in Civil Engineering, Transportation Planning, Geography or Town Planning? Sandwell, West Midlands
Recruiter: Sandwell Metropolitan Borough Council

REL Skip Driver

£27,711.00 - £30,559.00, Grade 6, 37 hours, Permanent
An opportunity exists in the Council’s Street Scene Services for an REL Skip Driver working from our depot at Castleford. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Mechanical and Electrical Engineer

£37,035- £41,511
We have an exciting opening to join our Property Team as a Mechanical & Electrical Engineer. Harrogate, North Yorkshire
Recruiter: North Yorkshire Council

Project Chargehand (4 Posts)

Grade 9 £31,344 - £33,253 per annum (Pending Pay Award)
We are looking for Project chargehands to lead teams working on highway maintenance and construction projects. Derbyshire
Recruiter: Derbyshire County Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW