Complex construction delays A249 scheme

14/05/2025 | GEORGE BARKER

Complex construction delays A249 scheme

Kent County Council (KCC) has announced further delays to the installation of a second bridge over the A249 and the realignment of the junction at Grovehurst Road in Sittingbourne, due to ‘the complexity of the construction’.

The works, which began in September 2023, were originally scheduled for completion in December last year but were extended an additional nine months - taking the new completion date into September this year.

When the original deadline was reached, KCC’s cabinet member for highways and transport, Neil Baker, said that the council understood that ‘major projects like this cause disruption but [it was] committed to minimising this as much as possible’, and that the council would ‘continue to monitor the situation’.

As well as construction difficulties, KCC has also stated that the delays are partially due to difficulties with co-ordinating utility companies, as there is work needed to move utility lines to clear the way for the scheme to proceed.

The new revised schedule that KCC has announced is as follows:

  • June: the gyratory will be opened to drivers
  • July: works to the Grovehurst Road on the Iwade side of A249 will be completed
  • August: works to the Kemsley side of the A249 will be completed
  • September: works to the existing bridge will be completed and the new bridge opened

The council added that traffic management planning is currently being used to reduce traffic congestion ‘as much as possible’ for the duration of the works, and that it will remain on the southbound exit slip road, as there are ongoing BT works that are taking place as well.

Simon Jones, KCC’s corporate director for growth, environment and transport, said: ‘Building the new bridge and making changes to the surrounding road network and utilities is a complex project. The local community has been very patient while the works have been progressing and we hope they will value the benefits of smoother and more reliable journeys this project will bring.’

Kent County Council has been approached for comment.

Highways InProfile

latest magazine issue
Highways jobs

Senior Street Cleanse Technician x 3 (CDC)

Grade 6 £25,981 - £26,815
We are about to embark on an ambitious programme of change in our city. Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Highways Development Officer

£37,280 - £40,777
This is an exciting time for a talented, self-driven professional to join us in the role of Highways Development Management Co-ordinator. Gloucester
Recruiter: Gloucestershire County Council

Principal Highways Development Officer

£48,226 - £51,35
This is an exciting time for a talented, self-driven professional to join us in the role of Highways Principal Development Management Co-ordinator . Gloucester, Gloucestershire
Recruiter: Gloucestershire County Council

Street Lighting Project Engineer

PO2 - £41,442 to £44,331
Help us keep our streets safe, efficient and ready for the future Greenwich, London (Greater)
Recruiter: Royal Borough of Greenwich

Principal Engineer - Highways Development Management

£47,181.00 - £50,269.00, Grade 11, 37 hours, Permanent
We are seeking a dedicated Principal Highways Development Management Engineer to join our team. Wakefield, West Yorkshire
Recruiter: Wakefield Council

Highways Development Management Engineer

£32,061.00 - £46,142.00, Career Grade 7-10, 37 hours, Permanent
Do you want to join a team helping to shape the future of Wakefield through HIghways Development Management? Wakefield, West Yorkshire
Recruiter: Wakefield Council

Highways Project Engineer

£31,537 - £42,839 per annum
Would you like to be part of our friendly, welcoming Highways team, proud to manage all aspects of the highway network? Boroughbridge, York
Recruiter: North Yorkshire Council

Highways Project Engineer

£31,537 - £42,839 per annum
Would you like to be part of our friendly, welcoming Highways team, proud to manage all aspects of the highway network? Skipton, North Yorkshire
Recruiter: North Yorkshire Council

Technician - Highway Inspector

Grade 8 £29,719 - £31,691 per annum
Within the Highways Maintenance Team we are looking for an enthusiastic, customer focused and experienced person Derbyshire
Recruiter: Derbyshire County Council

Highway Design and Construction Manager

Grade N, scp50 £62,443 to scp53 £65,663 per annum, plus essential car user allowance
We embrace AI to enhance our operations and to innovate our services. Bolton, Greater Manchester
Recruiter: Bolton Council

Technician - Highway Inspector

Grade 8 £29,719 - £31,691 per annum
At Derbyshire, we have been on a journey to transform the way we deliver highway services. Derbyshire
Recruiter: Derbyshire County Council

Team Leader (Maintenance Operations)

Grade 10 - £48,226 - £51,356
Cardiff is growing faster than any other capital city in Europe. Cardiff (Caerdydd)
Recruiter: Cardiff Council

Highways Supervisor

£Competitive
We have a fantastic opportunity for a permanent Highways Supervisor Forfar, Angus
Recruiter: Amey

Tree Surveyor

£Competitive
We are excited to offer fantastic opportunities for Permanent Tree Surveyors Scotland
Recruiter: Amey

Chief Operating Officer – South West Wales Corporate Joint Committee

£Competitive
We’re looking for a bold, visionary leader to take on the role of Chief Operating Officer Carmarthenshire (Sir Gaerfyrddin)
Recruiter: Carmarthenshire County Council

Clerk of Works - Highways

£Competitive
We have a fantastic opportunity for a Clerk of Works to join our dynamic NMC SW Account team at Polmadie. Glasgow, Glasgow City
Recruiter: Amey

Highways Supervisor

£Competitive
We have a fantastic opportunity for a permanent Highways Supervisor to join our NMC NE account in Kinross. Perth and Kinross
Recruiter: Amey

Planner - Highways

£Competitive
We have a fantastic opportunity for Permanent Planner – Highways to join our NMC SW Account. Glasgow City
Recruiter: Amey

Highways Maintenance Manager

£51,356 - £55,539 per annum
We are looking for an experienced Engineer to join the team as a Highways Maintenance Manager Selby, North Yorkshire
Recruiter: North Yorkshire Council

Highways Maintenance Manager

£51,356- £55,539 per annum
We are looking for an experienced Engineer to join the team as a Highways Maintenance Manager Brompton on Swale, Richmond
Recruiter: North Yorkshire Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW