The Long Read: The A9 dualling from beginning to end

27/09/2018
Dominic Browne

The A9 Dualling project is one of Scotland's largest ever transport infrastructure programmes. At a cost of some £3bn, the 11-stage scheme aims to upgrade 80 miles of single carriageway between Perth and Inverness. Dominic Browne speaks to project manager for A9 dualling, Jo Blewett, to find out the facts behind this massive scheme.

When is work on each section due to begin and end?

The Scottish Government is committed to dualling the A9 between Perth and Inverness by 2025. Road users are benefiting from the new dualled stretch between Kincraig and Dalraddy (pictured) which opened last year. Advance works are already underway on the section to be dualled between Luncarty and Pass of Birnam with the main construction works expected to start in the coming months.

Design work on the remaining nine dualling schemes is well advanced with draft Orders now published for eight of them, meaning that we have published draft Orders for 95% of the dualling programme. The last remaining scheme, Pass of Birnam to Tay Crossing, is at an earlier stage of design and we hope to identify a preferred option for this section later this year.

We are progressing with the preparation of the delivery programme, the timing and order of which is dependent on when individual schemes complete the statutory process.

How did you choose what sections to work on when?

The first two sections to be progressed to the construction stage were Kincraig to Dalraddy and Luncarty to Pass of Birnam. These were progressed first, simply because they were at a more advanced stage in the design process than the other sections. Many of the remaining sections are being progressed simultaneously.

We are progressing with the preparation of the delivery programme, the timing and order of which is dependent on when individual schemes complete the statutory process. Considerations such as minimising traffic disruption and proximity to other dualling schemes will also be factors that are considered when deciding the order of construction.

What is the finance model behind the work?

Procurement options continue to be explored with consideration being given to scheme sizes, procurement and funding models. Ongoing consultation with the construction industry is helping to shape the procurement strategy.

Why did you choose separate procurement processes for each of the 11 sections rather than a framework?

The fact that two of the dualling schemes were more advanced in design meant that a separate procurement process using Transport Scotland’s standard design and build form of contract was more appropriate. However going forward, the procurement process for the remaining sections is still under consideration.

What are the main challenges you have encountered so far?

The A9 passes through areas that are breathtaking and hugely important in terms of wildlife and landscape - not to mention people's homes. We are dealing with internationally environmentally designated sites; rock cuttings; building new bridges and widening existing major bridges; public utilities; dealing with the close proximity of the Highland Mainline Railway; and there are currently over 100 junctions that must be incorporated to provide access to adjacent property and communities.

Some very complex and demanding challenges lie ahead but, given our track record on other major projects, we are confident of delivery on time and on budget.

What are some of the main lessons and achievements you have made so far?

The ambitious A9 Dualling programme is more than just building roads. We recently launched the Highland Discovery app, which has been developed to promote tourism along the A9, including the less visited rural heartlands, and will help tourists navigate the many visitor attractions and facilities in and around the A9 corridor.

We have also established an educational initiative known as “Academy9”, a collaborative and evolving initiative, promoting STEM engagement within Scotland. The initiative brings together industry professionals, experienced educational professionals, to create truly unique experiences for school children of all ages and abilities. The programme also includes the goal of getting local pupils ready for local jobs, which the dualling programme will create.

Will the entire route be three star rating or above on the iRAP road safety model? If not why not and where will the gaps be?

The trunk road network in Scotland is not assessed in terms of the iRAP road safety model.

Are you expecting to encounter any areas of archaeology along the route – what have you found?

The main archaeological interest is the Killiecrankie battlefield. The existing road already runs through the battlefield site and the dualled route will impact further on this site. We therefore developed our dualling plans carefully taking into account available research and specialist advice, including consultation with Historic Environment Scotland (HES).

We carried out extensive surveys as part of early design work, but after receiving objections to the draft Orders, we agreed, in consultation with Historic Environment Scotland (HES) and Perth and Kinross Heritage Trust (PKHT), to bring forward additional survey work, comprising geophysical surveys, metal detecting and trial trenching. The next steps is to present the findings of the archaeological surveys to Historic Environment Scotland (HES) and the local community.

What protected species might you find along the route and how are you protecting their habitats or moving them?

The A9 from Perth to Inverness runs through a wide range of habitats important to Scotland’s protected fauna and flora. Some of these habitats are protected at a European level by Special Protection Areas (SPAs) for hen harrier and golden eagle, and the River Tay and River Spey Special Areas of Conservation (SAC), are designated for protection of salmon, lamprey and otter, as well as for freshwater pearl mussel.

Other habitats are recognised as nationally important such as the Sites of Special Scientific Interest (SSSI) and ancient woodland. Examples of European and nationally protected fauna include: beaver, wildcat, bats, red squirrel, water vole, pine marten, badger, freshwater pearl mussel, great crested newt, raptors and a range of other bird species (including Capercaillie, Crossbill, Osprey and Redwing).

Measures to avoid or mitigate impacts include programming construction to avoid sensitive breeding or migration periods. Crossing points below the road such as underpasses, culverts and wildlife tunnels have been incorporated into the design to facilitate animal movement, while strategic fencing will be provided to prevent animals from accessing the carriageway and to direct them to safe crossing points.

Planted mitigation includes planting with native woodland, shrub, heath and grassland species, and Outline Habitat and Peat Management Plans and Species Protection.

Transport Scotland reported a benefit to cost ratio (BCR) calculation in line with appraisal guidance of 1.01, which includes the benefits of relieving driver frustration. The programme BCR excluding driver frustration is 0.78 and including Wider Economic Benefits is 1.12. The benefit cost ratio for the project appears quite low by most standards. Do you feel that this demonstrates limitations of BCR model? Why is it so important to complete this despite the low return?

The A9 Dualling Case for Investment was published in September 2016 and sets out the business case for dualling the A9, between Perth and Inverness, from a strategic and socio-economic perspective. The benefit to cost ratio of the programme is only part of the wider rationale for the investment in the A9 Dualling Programme.

This ambitious programme will bring many benefits for road users, communities and businesses who live along or use this vital route to the Highlands and Islands and is fundamental to delivering sustainable economic growth, supporting jobs and enabling businesses to grow. When completed the dualled route will reduce journey times, improve journey time reliability and improve road safety for all users.

Is Transport Scotland concerned about induced traffic demand on the route?

We don’t have any concerns about increased traffic demand. Traffic flows are forecast to increase by between 2,500 and 4,600 AAWDT (Average Annual Weekday Traffic) following completion and the new dual carriageway will have sufficient capacity to accommodate this. In addition a corresponding reduction on traffic flows on other roads on the strategic road network is expected, with anywhere between 70-95% of the forecast traffic increase on the A9 a result of re-routing from the adjacent corridors i.e. existing trips already on the road network.

Are there any specified road materials for the dualling and if so what are they?

Transport Scotland’s bespoke TS2010 surfacing, which is more durable than many thin wearing courses and allows more use of locally sourced aggregates, is specified.

 

Traffex Road Expo Scotland will be taking place on Wednesday 31 October and Thursday 1 November and will be co-located with Bridges Scotland at the Royal Highland Centre in Edinburgh. Register for free today.

Running alongside Traffex Road Expo Scotland and Bridges Scotland will be CAV Scotland 2018, a Transport Scotland event, organised by Transport Network, that brings together global experts in connected and autonomous vehicles with live demonstrations.

Latest Issue

latest magazine issue

Inside

  • Smart motorways' BCR problem
  • New lighting decision support tool

 

 

View the latest issue


Highways jobs

Highway Engineer - Reactive Maintenance

£35,354 - £40,506 incl. LWA, plus £963 car allowance
We make a difference to the environment we live in. Come and help us manage our highway infrastructure. Bracknell, Berkshire
Recruiter: Bracknell Forest Borough Council

Maintenance Manager

£43,857 to £47,782
We are currently looking for a strong candidate to take up the role of Maintenance Manager at Area 6 Boroughbridge. Boroughbridge, York
Recruiter: North Yorkshire County Council

Engineer Sustainable Development

£32,234 - £36,922 per annum
To help support this key area of work, we are looking for an enthusiastic, experienced and forward thinking Engineer to... Stafford, Staffordshire
Recruiter: Staffordshire County Council

Senior Engineer (Streetscene)

£40,632 - £45,594
We are looking for 2 Senior Engineers to join our team to help deliver effective Capital and Revenue investments programmes to... Hackney, London (Greater)
Recruiter: Hackney London Borough Council

Neighbourhood Highway Officers - West and North

£28,672 per annum
We are seeking a recruit two Neighbourhood Highway Officers (NHO), to be based in Okehampton and Tiverton, Devon. Devon
Recruiter: Devon County Council

Warehouse Assistant/Driver

£20,903 - £24,491 per annum
The successful applicants will work as part of a team in a busy work environment to carry out warehouse and... Sandwell, West Midlands
Recruiter: Sandwell Metropolitan Borough Council

Planning Policy Manager

£61.470 - £64.704
Be part of Greenwich's vision to successfully accommodate a high level of sustainable growth, which... Greenwich, London (Greater)
Recruiter: Royal Borough of Greenwich

Refuse Driver (Rolling Advert - applications checked weekly)

£30.032 - £31.610
It is an exciting time in Street Services at the Royal Borough of Greenwich. Be part of a team who are... Greenwich, London (Greater)
Recruiter: Royal Borough of Greenwich

Traffic Engineer

£32,301 - £37,491
We are currently looking for an experienced Traffic Engineer to join our Design & Engineering team.  London (Greater)
Recruiter: Hackney London Borough Council

Apprentice Civil Engineering Technician

£12,656.10
This opportunity is primarily based out of our West Offices in the heart of York. York, North Yorkshire
Recruiter: City of York Council

Traffic Enforcement Manager

£40,869 - £43,860
As part of a major service transformation, Haringey is seeking to recruit to a new number of new positions. Haringey, London (Greater)
Recruiter: Haringey London Borough Council

Refuse Driver

£30032 - £31610 per annum + (amount shown is salary plus allowances)
Refuse Driver (LGV Chargehand Driver)(starting total pay of £30,032 - this is made up of the base grade salary plus contractual overtime and allowance England, London, Woolwich
Recruiter: Royal Borough of Greenwich

Corporate Director (Environment, Communities & Leisure)

Up to £83,424 (pay award pending)
As one of our two Corporate Directors reporting to the Chief Executive to form our Senior Leadership Team your... Gedling, Nottingham
Recruiter: Gedling Borough Council

Senior Infrastructure Engineer

£45.834 - £56.141
This is a great role in a vibrant and growing team; we’re looking for people with significant experience in... Greenwich, London (Greater)
Recruiter: Royal Borough of Greenwich

Parking Service Business Manager

£43,860 - £46,839
As part of a major service transformation, Haringey is seeking to recruit to a new number of new positions. Haringey, London (Greater)
Recruiter: Haringey London Borough Council

Roads Technician

£18,812 - £23,791
This is a great opportunity for you to join Lincolnshire County Council's Technical Services Partnership as... Lincolnshire
Recruiter: Lincolnshire County Council

Roads Engineer

£25,991 - £35,745
We are looking for people to join one of our three Roads teams, made up of around 30 friendly and enthusiastic professionals. Lincolnshire
Recruiter: Lincolnshire County Council

Senior Project Manager

Up to £50,823 per annum
The role of this post is to oversee the project management, development and implementation of the County Council’s Major Transport Projects.. Leicestershire
Recruiter: Leicestershire County Council

Programme and Change Delivery Manager (Spatial Planning and Urban Design)

£43,833 - £53,115 Depending on skills and experience
Are you a change delivery manager with expertise in England’s local government spatial planning and urban design sector? Wandsworth, London (Greater)
Recruiter: London Borough of Richmond upon Thames and London Borough of Wandsworth

Bridges Manager – Highways and Transportation

£49,320 to £57,376
You will be responsible for... Northallerton, North Yorkshire
Recruiter: North Yorkshire County Council

Highways Presents

Highways on Fridays

Register now!

Latest Video